HomeMy WebLinkAbout2017-08-21-J01P SW Area Trunk Sewer Extension_Change Order 2ME►4 Waukee , W1 THE KEY TO GOOD LIVING AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: August 21, 2017 AGENDA ITEM: Consideration of approval of Change Order No. 2 to Pohlmeier Construction, Inc. for the Southwest Area Trunk Sewer Extension Project decreasing the contract in the amount by $10,126.00 FORMAT: Consent Agenda SYNOPSIS INCLUDING PRO & CON: The change order is to compensate the Contractor for removing and replacing 20 LF of 24-inch CMP, core drilling and installing an 8-inch sewer stub at MH-1, and seeding all areas scheduled to be sodded. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order decreases the contract price by $10,126.00. COMMISSIONIBOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the consent agenda. ATTACHMENTS: I. Change Order No. 2 II. Letter of Recommendation PREPARED BY: Beth Richardson/Rudy Koester7-sK REVIEWED BY: John Gibson PUBLIC NOTICE INFORMATION — NAME OF PUBLICATION: DATE OF PUBLICATION: VEENSTRA & KIMM, INC. 3000 Westown Parkway • West Des Moines, Iowa 50266-1320 515-225-8000.515-225-7848 (FAX) • 800-247-8000 (WATS) August 15, 2017 John R. Gibson Public Works Director City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA SOUTHWEST AREA TRUNK SEWER EXTENSION CHANGE ORDER NO. 2 Enclosed are three copies of Change Order No. 2 for the Southwest Area Trunk Sewer Extension project under the contract between the City of Waukee and Pohlmeier Construction, Inc. Change Order No. 2 is to compensate the Contractor for removing and replacing 20 LF of 24-inch CMP, core drilling and installing an 8-inch sewer stub at MH-1, and seeding all areas scheduled to be sodded. Change Order No. 2 decreases the contract price by a total of $10,126.00. Veenstra & Kimm, Inc. recommends approval of Change Order No. 2. Please sign all copies of Change Order No. 2 in the spaces provided. Return one signed copy of Change Order No. 2 to our office and one signed copy to Pohlmeier Construction, Inc. West Des Moines, /A. Coralville, IA • Mason City, IA - Sioux City, IA • Rock Island, IL • Springfield, If • Liberty, MO John R. Gibson August 15, 2017 Page 2 If you have any questions or comments, please contact us at 225-8000. VEENSTRA & KIMM, INC. X� +� Jordan Kappos JDK 275274 Enclosure cc: Rudy Koester, City of Waukee (via e-mail) Becky Schuett, City of Waukee (via e-mail) Pohlmeier Construction, Inc. w/ enclosure August 15, 2017 WAUKEE, IOWA SOUTHWEST AREA TRUNK SEWER EXTENSION VEENSTRA & KIMM, INC. 3000 Westown Parkway • West Des Moines, Iowa 50266-1320 515-225-8000 9 515-225-7848(FAX) • 800-241-8000(WATS) CHANGE ORDER NO. 2 Change Order No. 2 is to compensate the Contractor for miscellaneous items related to the project. Change Order No. 2 includes the following items: Item Estimated Extended No. Description Unit Quantity Unit Price Price 1.5 Sodding SQ (282) $75.00 ($21,150.00) 1.21 Remove and Replace 20 LF of 24" LS 1 $1,000.00 $1,000.00 CMP 1.22 Core Drill MH #1 and Install 8" I.S 1 $1,000.00 $1,000.00 Sewer Stub 1.23 Seed All Areas Scheduled to be LS 1 $9,024.00 $9,024.00 Sodded Total ($10,126.00) Change Order No. 2 decreases the contract price by a total of $10,126.00. POHLMEIER CONSTRUCTION, INC. By Title Date!(LTh% VEENSTRA & KIMM, INC. By ( 2doz Title Project Engineer Date K / (S /ZJI % CITY OF WAUKEE, IOWA By Ti ATTEST: Title 275274 Page 1 of 1