HomeMy WebLinkAbout2017-10-02-J01K Southfork Dam Outlet Improvements_Pmt Est 1NO Waukee •IWI1 THE KEY TO GOOD LIVING /:[61:1hN7:111111U11Il►r" CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: October 2, 2017 AGENDA ITEM: Consideration of approval of Partial Payment Estimate No. I (Final) to J & K Contracting, LLC for the Southfork Dam Outlet Improvements in the amount of $62,841.41 FORMAT: Consent Agenda SYNOPSIS INCLUDING PRO & CON: J & K Contracting, LLC has requested Payment Estimate No. 1 (Final) for the work completed on the Southfork Dam Outlet Improvements project in the amount of $62,841.41. V & K has reviewed the payment estimate and recommends payment. Partial Payment No. I(Final) covers the entire project. FISCAL IMPACT INCLUDING COSTBENEFIT ANALYSIS: $62,841.41 COMMISSIONBOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Partial Payment No. 1 (Final) ATTACHMENTS: 1. Partial Payment No. 1 (Final) II. Letter of Recommendation PREPARED BY: Beth Richard Koester y— REVIEWED BY: John Gibson PUBLIC NOTICE INFORMATION -- NAME OF PUBLICATION: DATE OF PUBLICATION: VEE VSTRA & 8®I/YiM, M'9.... A00 Wcstown Parkway • West Des Moines, Iowa 50266- R20 .575-225-8000 • 5IS-22J848 (FAX) • 600-241-8000 ! t,A7ii September 26, 2017 John R. Gibson Director of Public Works City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA SOUTHFORK DAM OUTLET IMPROVEMENTS CHANGE ORDER NO. 1 PARTIAL PAYMENT NO. 1 (FINAL) Enclosed are three signed copies of Change Order No. 1 and Partial Payment No. 1 (Final) in accordance with the contract between the City of Waukee and J&K Contracting, LLC for the Southfork Dam Outlet Improvements project. Change Order No. 1 is to adjust the plan quantities to the as -constructed quantities and for extra concrete underneath the outlet. Partial Payment No. 1 (Final) covers the entire project. We recommend payment by the City Council of the City of Waukee to J&K Contracting, LLC in the amount of $62,841.41. We also recommend the retainage in the amount of $3,307.44 be paid 31 days after acceptance of the work by the City of Waukee. Please execute all copies of Change Order No. 1 and Partial Payment No. 1 (Final) in the spaces provided. Please return one copy of each to Veenstra & Kimm, Inc., forward one copy to J&K Contracting, LLC with payment, and retain one copy for your files. If you have any questions or comments, please contact us at 225-8000. VEENSTRA & KIMM, INC. Original Signed by Andy Willcuts Andy R. Willcuts ARW:dml 275268 Enclosures cc: Becky Schuett, City of Waukee w/enclosures Rudy Koester, City of Waukee w/enclosures West Des Moines, IA • Coralville, IA • Macon City, to • .Sioux City, IA • Ruck Island It • Springfield, It • tiGerfy MO �r_ = VEENSTRA & KIMM, INC -_ _ 3000 Westown Parkway West Des Moines, Iowa 50266 1320 - — 515-225-8000 515-225-7848(FAx) 800.241-8000 (WATSJ Date: September 20, 2017 PAY ESTIMATE NO. 1 (FINAL) Project Title SOUTHFORK DAM OUTLET Contractor J&K Contracting, LLC IMPROVEMENTS 1307 E Lincoln Way CITY OF WAUKEE, IOWA Ames, IA 50010 Original Contract Amount & Date April 17, 2017 $64,000.00 Pay Period April 17, 2017 to September 15, 2017 BID ITEMS Description Unit Estimated Quantity I Unit Price Extended Price Quantity Complete Value Completed 1.1 Mobilization LS 1 $ 4,300.00 $ 4,300.00 1.00 $ 4,300.00 1.2 Hydroseeding LS 1 $ 4,100.00 $ 4,100.00 1.00 $ 4,100.00 1.3 Clearing & Grubbing LS 1 $ 3,900.00 $ 3,900.00 1.00 $ 3,900.00 1.4 Erosion and Sediment Control LS 1 $ 5,300.00 $ 5,300.00 1.00 $ 5,300.00 1.5 Bank Shaping LS 1 $ 12,304.00 $ 12,304.00 1.00 $ 12,304.00 1.6 Gabion Baskets SF 288 $ 22.00 $ 6,336.00 288 $ 6,336.00 1.7 Rip -Rap Tons 220 $ 89.00 $ 19,580.00 220 $ 19,580.00 1.8 Rock Check Dams LS 1 $ 1,880.00 $ 1,880.00 1.00 $ 1,880.00 1.9 Additional Rip -Rap for Check Dams Tons 20 $ 65.00 $ 1,300.00 20 $ 1,300.00 1.10 Permanent Rolled Erosion Control SY 500 $ 10.00 $ 5,000.00 600 $ 6,000.00 TOTAL CONTRACT $ 64,000.00 $ 65,000.00 V-K Job No. 275268 SUMMARY Contract Price Value Completed Original Contract Price $64,000.00 $ 65,000.00 Approved Change Orders (list each) TOTAL ALL CHANGE No. 1 $ 2,148.85 $ 1,148.85 ORDERS $ 2,148.85 $ 1,148.85 Revised Contract Price $ 66,148.85 $ 66,148.85 Materials Stored $ - Value of Completed Work and Materials Stored $ 66,148.85 Less Retained Percentage (5%) $ 3,307.44 Net Amount Due This Estimate $ 62,841.41 Less Estimates) Previously Approved No.1 No.2 No.3 No.4 No.S N o.6 No. 7 No. 8 No. 9 Less Total Pay Estimates Previously Approved $ - Amount Due This Estimate $ 62,841 .41 The amount $ 62,841.41 is recommended for approval for payment in accordance with the terms of the contract. The amount of $ 3,307.44 is payable 31 days after final acceptance of the project. Quantities Complete Submitted By: Recommended By: Approved By: J&K Contracting, LLC Veenssttrra & Kimm, Inc. City of Waukee, Iowa Sign ure Signature Signature P. 1-7n 9 ;AG t t Title Title Title Date Date Date V-K Job No. 275268