HomeMy WebLinkAbout2017-11-06-J01M LWC Regional Lift Station Expansion_Pmt Est 7NO Waukee fr 1 r THE KEY TO GOOD LIVING AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: November 6, 2017 AGENDA ITEM: Consideration of approval of Partial Payment Estimate No. 7 (Final) to Synergy Contracting LLC for the Little Walnut Creek Regional Lift Station Expansion Project in the amount of $47,719.47 FORMAT: Consent Agenda SYNOPSIS INCLUDING PRO & CON: Synergy Contracting LLC has requested Payment Estimate No. 7 (Final) for the work completed on Little Walnut Creek Regional Lift Station Expansion project in the amount of $47,719.47, Veenstra & Kimm, Inc. has reviewed the payment estimate and recommends payment. Partial Payment No. 7 (Final) is for completion of all work at the lift station and surface restoration FISCAL IMPACT INCLUDING COSTIBENEFIT ANALYSIS: $47,719.47 COMMISSIONBOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Partial Payment No. 7 (Final) ATTACHMENTS: I. Letter of Recommendation II. Partial Payment No. 7 (Final) PREPARED BY: Beth Richardson/Rudy Koester REVIEWED BY: John Gibson PUBLIC NOTICE INFORMATION — NAME OF PUBLICATION: DATE OF PUBLICATION: VEENSTRA & KIMM, INC. 3000 Westown Parkway • West Des Moines, Iowa 50266-1320 515-225-8000.515-225-7848(FAA? • 800-241-8000 (WATS) October 31, 2017 John Gibson City of Waukee 805 University Avenue Waukee, IA 50263 WAUKEE, IOWA LITTLE WALNUT CREEK REGIONAL LIFT STATION EXPANSION CHANGE ORDER NO. 3 AND PARTIAL PAYMENT NO. 7 (FINAL) Enclosed are three signed copies each of Change Order No. 3 and Partial Payment No. 7 (Final) in accordance with the contract between the City of Waukee and Synergy Contracting LLC for the Little Walnut Creek Regional Lift Station Expansion project. Change Order No. 3 is for additional time and materials due to an incorrect water main locate. Change Order No. 3 will increase the price for the Little Walnut Creek Regional Lift Station Expansion project by a total of $17,301.02. We recommend approval of Change Order No. 3 by the City Council of the City of Waukee. Partial Payment No. 7 (Final) is for completion of all work at the lift station and surface restoration. We recommend payment by the City Council of the City of Waukee to Synergy Contracting LLC in the amount of $47,719.47. We also recommend the retainage in the amount of $96,434.65 be paid 31 days after acceptance of the work by the City of Waukee. As per the Bond, al I payments relating to this project should be directed to Northern Escrow, Inc., 1276 So. Robert St., West St. Paul, MN 55118. Please execute all copies of Change Order No. 3 and Partial Payment No. 7 (Final) in the spaces provided. Return one copy to Veenstra & Kimm, Inc., forward one copy to Synergy Contracting LLC with payment, and retain one copy for your files. If you have any questions or comments, please contact us at 225-8000. VEEC� &KIMM, INC. Sara Kappo 275275 Enclosures cc: Rudy Koester, City of Waukee w/enclosure Becky Schuett, City of Waukee w/enclosure Synergy Contracting w/enclosure West Des Moines, IA •Coralville, iA • Mason City, IA • Sioux City, IA - Moline, IL • Springfield, IL • Liberty, MO _- - VEENSTRA & KIMM. INC. __ J000 weswwn ra.kway Wesl oes rannws, Irnva snzara'Irn 515-2554000 515-225Je48(FA,1 801241-8000(WAiS) Date: October 30, 2017 PA Y ESTIMA TE NO. 7(FINAL) Project Title Little Walnut Creek Regional Lift Station Expansion Waukee, Iowa Contractor Synergy Contracting LLC 1120 2nd Street NE PO Box 388 Bondurant, IA 50035 Amount Contract Amount &Date $1,783,600.00 February 21, 2017 Pay Period 9/28/17 • 10/30/17 BID ITEMS Description Unit Estimated Quantity Unit Price Extended Price Quantity Completed Value Completed 1.1 Mobilization LS xxxxx xxxxx $ 246,665.00 100% $246,665.00 1.2 Traffic Control LS xxxxx xxxxx $ 9,000-00 100 % $9,000.00 1.3 Erosion Control LS xxxxx xxxxx $ 6,000.00 100 % $6,000.00 1.4 Surface Restoration LS xxxxx xxxxx $ 15,000.00 100 % $15,000.06 1.5 Lift Station Modifications L5 xxxxx xxxxx $ 400,000.00 100 % $400,000.00 1.6 16" Force Main Augered in 24" Steel Casing LF 220 $ 273.00 $ 60,060.00 220 $60,060.00 1.7 16" Force Main Directional Bored in Place or in Open Cut LF 9,525 $ 103.00 $ 981,075.00 9,525 $981,075.00 1.8 Air Release Manholes EA 3 $ 18,200.00 $ 54,600.00 3 $54,600.06 1.9 Line Existing Manholes EA 4 $ 2,800.00 $ 11,200.00 4 $11,200.00 Total $ 1,783,600.00 $ 1,783,600.00 SUMMARY Contract Price Value Completed Original Contract Price $1,783,600.00 $1,783,600.00 Approved Change Order(s) No.1 $124,042.00 $124,042.05 No.2 $3,750.00 $3,750.00 No.3 $17,301.02 $17,301.02 Revised Contract Price $1,928,693.02 $1,928,693.02 Less Retained Percentage (5 k) $96,434.65 Net Amount Due This Estimate $1,832,258.37 Less Estimate(s) Previously Approved No.1 $374,319.87 No.2 $387,139.18 No. 3 $290,300.02 No.4 $167,798.97 No.5 $207,369.17 No.6 $357,611.69 Total Previously Approved $1,784,538.90 Percent Complete 100/ Amount Due This Estimate $47,719.47 The amount of $47,719.47 is recommended for approval for payment in accordance with the terms of the Contract. The amount of $96,434.65 is payable 31 days after final acceptance of the project. Prepared By: Synergy Contracting LLC Recommended By: Veenstra & Kimm, Inc. Approved By: City of Waukee Si lature Signatur Signature T' Title I 1 �C / Title Date Date Date V&K lob No. 275275