AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: January 18, 2016
AGENDA ITEM: Consideration of approval of a Contract Modification No. 18 to the Iowa
Department of Transportation for the 105th Street/Alice's Road I-80 Interchange
Project with a net change in the contract of $0.00
FORMAT: Resolution
SYNOPSIS INCLUDING PRO & CON:
The contract has a completion date of November 15, 2015. The adjacent City of Waukee project (Local
Project) has a completion date of November 26, 2015. The contract completion
date will be adjacent to the November 26, 2015 to maintain consistency with
other projects within the Grand Prairie Parkway corridor. No price adjustments
will be associated with this change in Completion Date.
FISCAL IMPACT INCLUDING COSTBENEFIT ANALYSIS:
COMMISSIONBOARDICOMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Contract Modification No. 18 to the Iowa Department of
Transportation for the 105`h Street/Alice's Road I-80 Interchange Project with a
net change in the contract of $0.00.
ATTACHMENTS: I. Contract Modification 18
PREPARED BY: Beth Richardson
E
REVIEWED BY: John Gibson
PUBLIC NOTICE INFORMATION --
NAME OF PUBLICATION:
DATE OF PUBLICATION:
GJ Contract Modification
11/9/2015 9:46 AM
Iowa Department of Transportation
FieldManager 5.Oa
Contract: 25.0803-175, PCC PAVEMENT - GRADE AND NEW
Cont. Mod. Revision Cont. Mod. Net Change Awarded Contract Amount
Number Number Date
18 11/9/2015 $0.00 $13,423,922.46
Route Entered By
HWY 1-80 (C31912) Jennifer Strunk
Contract Location
DALLASIMN-080-3(175)119-0E-25
Short Description
Adjust Completion Date
Description of Changes
NON SUBSTANTIAL
Adjust Completion Date to November 26, 2015.
The contract has a Completion Date of November 15, 2015. The adjacent City of Waukee project has a Completion Date of
November 26, 2015. The Contract Completion Date will be adjust to November 26, 2015 to maintain consistency with other
projects within the Grand Prairie Parkway corridor. No price adjustments will be associated with this change in Completion
Date.
When authorized, the contractor agrees to perform the work outlined above in accordance with provisions of the contract
documents.