HomeMy WebLinkAbout2016-01-18-J01I Alices Rd Traffic Signalization_Change Order 4► O Waukee f.IY SHE KEY TO GOOD LIVING AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: January 18, 2016 AGENDA ITEM: Consideration of approval of Change Order No. 4 to Howrey Construction for the Traffic Signalization/Trail — SE Alices Road From SE Ashworth Road to SE University Avenue IDOT Contract ID / Accounting ID: 25-8177-617.31484 increasing the contract amount by $40,230.35 FORMAT: Consent Agenda SYNOPSIS INCLUDING PRO & CON: The change order is for: a. Additional payment to remove and reinstall handholes and conduit at Ashworth Road due to water main construction b. Increase quantity of wire listed in the Schedule of values for signal to operate per plan c. Additional square footage to pay for signage switch from "SE Alices Rd" to "Grand Prairie Pkwy" d. Addition of two illuminated "No Right on Red" signs at the intersection of SE University Ave and SE Alices Road e. Addition of two "Stop Here on Red" signs on Ashworth Road FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: increase the contract by $40,230.35. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: The net result of this change order RECOMMENDATION: Approve the consent agenda. ATTACHMENTS: I. Change Order No. 4 lI. Foth Infrastructure and Environment, LLC letter of recommendation PREPARED BY: Beth Richardson REVIEWED BY: John Gibson PUBLIC NOTICE INFORMATI N — NAME OF PUBLICATION: DATE OF PUBLICATION: *v.vFoth January 12, 2016 John Gibson Director of Public Works 805 University Avenue Waukee, IA 50263 RE: Change Order #4 Traffic Signalization/Trail - SE Alices Road From SE Ashworth Road to SE University Avenue IDOT Contract ID / Accounting ID: 25-8177-617 / 31484 Dear Mr. Gibson: Attached please find a detailed Change Order for City Council approval on January 18, 2016. Change Description Additional payment to remove and reinstall handholes and conduit at Ashworth Road due to water main construction. Increase quantity of wire listed in the Schedule of values for signal to operate per plan. Additional square footage to pay for signage switch from "SE Alices Rd" to "Grand Prairie Pkwy". Addition of two Illuminated "No Right on Red" signs at the intersection of SE University Ave & SE Alices Rd. Addition of two "Stop Here on Red" signs on Ashworth Road. We have reviewed the submitted quotes from Howrey Construction and Iowa Signal and they appear to be in order with current industry pricing. If City Staff concurs with this pricing, it is recommended the City of Waukee increase the contract price in the amount of 40$ ,230.35 to complete the work associated with Change Order #04. Please let me know if you have any questions or need additional information. Sincerely, Foth Infrastructure and Environment, LLC Joshua C. DeBower, P.E. Lead Civil Engineer Encl: Change Order #4 dated 1/12/16 8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 Fax: (515) 254-1642 Form 830240 04-08 Contract Accounting ID No.: 31484 Kind of Work: TRAFFIC SIGNALIZATION Contractor: HOWREY CONSTRUCTION ` \ Iowa Department of Transportation '77 Change Order Non -Substantial Non - Part Part No. 4 Substantial ❑ ❑ Concurrence Date County: DALLAS Project No: HDP-8177(617)--71-25 Date Prepared: 1/12/2016 You are hereby authorized to make the following changes to the contract documents. A - Description of change to be made or extra work to be done: 7004 - Increase quantity of Traffic Signalization by $40,230.35 B - Reason for change or extra work: 7004 - Increase in amount is due to five components: 1) During construction, handholes and conduit needed to be removed then reinstalled for circumstances contractor had no control of. 2) Quantity of Detector Cable and Deteector Lead-in Cable listed on the schedule of unit values was significantly lower than of the wire needed for the signal to appropriately detect vehicle movements. 3) Additional Sq Ft for switching road sign from "SE Alices Rd" to "Grand Prairie Parkway'. 4) Installation of two Illuminated "No Right on Red" signs at the intersection of SE University Ave and BE Alices Rd. 5) Installation of two "Stop here on Red" signs on BE Ashworth Rd. (Continued on reverse side) Approved District Engineer Date Project Engineer Receipt is acknowledge of this change or extra work and terms of settlement are hereby agreed to. Approved contingent upon funds being available under the existing project agreement or upon additional Federal -aid funds being made available by a modified project agreement. Date For the Division Administrator Federal Highway Administration Contractor By Approved Assistant Engineer DISTRIBUTION: Project Engineer- Forward original to District District- Non -substantial - Forward original and one copy to the Office of Construction and two copies back to the Project Engineer. - Substantial - Forward original and two copies to the Office of Construction. Date Date Date Accounting ID No. 131 1 1418141 1 1 2 3 4 5 6 C-1 - Settlement for cost of work to be made as follows: 7004 - Increase contract by the following: Change Order No. 1) $4,018.20 for Remove & Reinstallation of handholes and conduit 2) $22,972.65 for the additional wire needed to provide signalization per plan 3) $639.50 for additional Sq. Footage of Signage 4) $12,150 for two Illuminated "No Right on Red" Signs 5) $450 for two "Stop Here on Red" signs with posts C-2 - Justification for cost(s) 7004 - Refer to attached documentation for justification of costs. D - ITEMS INCLUDED IN CONTRACT If Credit Add"CR" Change No. Line Item Number Unit Price xxx Quantity xxx Amount xx 7 004 2525-0000100 1.000 40,230.35 $ 40,230.35 7 $ 7 $ 7 $ 7 $ 7 $ 7 $ TOTAL $ 40,230.35 E - ITEMS NOT INCLUDED IN CONTRACT If Credit Add"CR" Change No. Item Description Item Number Function Code Unit Price xxx Quantity xxx Amount Ax 8 $ 8 $ 8 $ 8 $ g $ 8 $ g $ TOTAL $