HomeMy WebLinkAbout2016-03-17-D01 Bluestem Lift Station 14 - Award Contract AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: March 17, 2016 AGENDA ITEM: Consideration of approval of a resolution awarding contract [Waukee Bluestem Lift Station #14 Improvement Project] FORMAT: Resolution SYNOPSIS INCLUDING PRO & CON: The bid letting was held at Waukee City Hall on February 29, 2016, at 2:00 p.m. One apparent bid was received, submitted by J&K Contracting of Ames, IA, in the amount of $948,000.00. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $948,000.00 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: City staff recommends awarding the contract to J&K Contracting of Ames, IA, in the amount of $948,000.00. RECOMMENDATION: Approve the resolution awarding contract to J&K Contracting of Ames, IA, in the amount of $948,000.00. ATTACHMENTS: I. Proposed resolution II. Bid tabulation PREPARED BY: Becky Schuett REVIEWED BY: RESOLUTION 16- RESOLUTION MAKING AWARD OF CONSTRUCTION CONTRACT FOR THE BLUESTEM LIFT STATION #14 IMPROVEMENTS BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WAUKEE, STATE OF IOWA: Section 1. That the following bid for the construction of certain public improvements described in general as the Bluestem Lift Station #14 Improvements, described in the plans and specifications heretofore adopted by this Council on March 7, 2016, be and is hereby accepted, the same being the lowest responsive, responsible bid received for such work, as follows: Contractor: J&K Contracting of Ames, IA Amount of bid: $948,000.00 Portion of project: All construction work Section 2. That the Mayor and Clerk are hereby directed to execute the contract with the contractor for the construction of the public improvements, such contract not to be binding on the City until approved by this Council. PASSED AND APPROVED this 17th day of March, 2016. Mayor ATTEST: City Clerk N:\PROJECTS\WAK 2214027\CLER\CORRESPONDENCE\WAUK EE 3.DOCX4/27/2015 4:41 PM May 14, 2015 Mr. John Gibson City of Waukee 805 University Avenue Waukee, IA 50263 RE: Bluestem Lift Station #14 Imp. Waukee, IA MEC 2214027 Dear John: As you are aware, the Bluestem Lift Station project received only one bid and was substantially over budget. We believe this was due to multiple factors. The estimate was low, and a great deal of work currently bidding, is creating very little competition. We advertised the project extensively, had 21 plan holders and were disappointed we only had one bidder. McClure reached out to an industry friend to encourage them to submit a bid to the prime contractor for the directional drilling operations with the expectation of significant savings. Unfortunately, after the subcontractor and prime bidder were able to communicate about the work items in detail, they determined the savings would be nominal and not worth pursuing (less than $10,000). The prime bidder, J & K Contracting, was able to find some savings from the original bid and will offer that via change order, if the project is awarded. It is much less than we were hoping for. We believe the options for achieving cost savings on the project have been exhausted. Given the schedule constraints the city has to work with, we recommend you award the contract at this time, in-lieu of re-bidding the project. Sincerely, McClure Engineering Company Curt Kampman, P.E. CK:db