HomeMy WebLinkAbout2016-04-04-J01K Original Sanitary Sewer Rehab Phase I Pmt Est 2Waukee • �W1 THE KEY 70 GOOD LIVING AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: April 4, 2016 AGENDA ITEM: Consideration of approval of Partial Payment Estimate No. 2 to Hydra-Klean, LLC for the Original Sanitary Sewer Collection System Rehabilitation — Phase 1 Project in the amount of $11,287.87 FORMAT: Consent Agenda SYNOPSIS INCLUDING PRO & CON: Partial Payment No. 2 is for post lining televising and service grouting. FISCAL IMPACT INCLUDING COSTBENEFIT ANALYSIS: $11,287.87 COMMISSION/BOARD/COMMITTEE COMMENT: Hydro-Klean, LLC has requested Payment Estimate No. 2for the work completed on the Original Sanitary Sewer Collection System Rehabilitation — Phase 1 project in the amount of $11,287.87. Veenstra & Kimm has reviewed the payment estimate and recommends payment. STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Partial Payment No. 2 ATTACHMENTS: I. Partial Payment No. 2 II. Letter of Recommendation PREPARED BY: 1:7*11*143ADIQ-we Beth Richardson John Gibson PUBLIC NOTICE INFORMATION — NAME OF PUBLICATION: DATE OF PUBLICATION: VEENSTRA & KIMM, INC. 3000 Westown Parkway • West Des Moines, Iowa 50266-1320 515-225-8000 • 515-225-7848(FAX) • 800-241-8000(WATS) March 28, 2016 John Gibson City of Waukee 805 University Avenue Waukee, IA 50263 WAUKEE, IOWA ORIGINAL SANITARY SEWER COLLECTION SYSTEM REHABILITATION - PHASE 1 PARTIAL PAYMENT NO. 2 Enclosed are three signed copies of Partial Payment No. 2 in accordance with the contract between the City of Waukee and Hydro-Klean LLC for the Original Sanitary Sewer Collection System Rehabilitation - Phase 1 project. We recommend payment by the City Council of the City of Waukee to Hydro-Klean LLC in the amount of $11,287.87. Partial Payment No. 2 is for post lining televising and service grouting. Please execute all three copies of Partial Payment No. 2 in the spaces provided. Return one copy to Veenstra & Kimm, Inc., forward one copy to Hydro-Klean LLC with payment, and retain one copy for your files. If you have any questions or comments, please contact us at 225-8000. VEENSTRA & KIMM, IINNC. Sara Kappos SKK 275261 Enclosures cc: Tim L. Royer, City of Waukee w/enclosure Brad Deets, City of Waukee w/enclosure Becky Schuett, City of Waukee w/enclosure Hydro-Klean LLC w/enclosure West Des Moines • Coralville • Omaha -Moline • Mason City • Sioux City • Liberty VEENSTRA & K(MM, INC. ESTIMATE OF CONSTRUCTION COMPLETED PARTIAL PAYMENT NO. 2 PROJECT TITLE: Original Sanitary Sewer Collection System Rehabilitation - Phase I - CITY OF WAUKEE, 101VA Contractor: Hvdro-Klean 1-1-C Date: 3.24-16 Original Contract Amount: S165,097.82 Pav Period: December 1, 2015, to March 23, 2016 BID ITEMS `.iNO, DESCR!P110N CNI! CJL'AN II IA 11PRica A'::i I l'U'.IPL%rLC ic,[14ii LSIIMAILJJ n)RIC-IX1�1.1 AI [HORIL1U IItiO.C.0. 51 CO',PLULU 10DO6 1.1 Mobilization LS 1-000 1.000 1.000 $3,441.00 $3,441.00 1.2 Traffic Control LS 1.000 1.000 1.000 $200.00 $200.00 1.3 10-inch Sanitary Sewer Televising LF 7,770.000 0.000 0.000 $0.71 $0.00 1.4 10-inch Sanitary Sewer Cleaning LF 3,885.000 0.000 0.000 $1.17 $0.00 1.5 10-inch Sanitary Sewer Cured -in -Place LF 3,885,000 0.000 0.000 $20.301 $0.00 1.6 lReinstate, Service Ea. 1 124.000 124.0001 129.000 $50.00 $6,450.00 1.7 Grout Service Ea. 124.000 124.000 31.000 $236.58 $7,333.98 1.8 12-inch Sanitary Sewer Televising LF 2,350.000 2 350.000 2,660,000 $0.71 $1,888.60 1.9 12-inch Sanitary Sewer Cleaning LF 1,175.000 1175,000 1330.000 $1.17 $1,556.10 1,10 12-inch Sanitary Sewer Cured -in -Place LF 1,175.000 1,175.000 1,330.000 $26.00 $34,580.00 1.11 Heavy Cleaning LF 680.000 680.000 690.000 $5.00 $3,450.00 Original Conb'a et Value Completed S58,899.68 2.1 8" Sanitary Sewer Televising LF 7,700.000 7,728.000 $0.71 $5,486.88 2.2 8" Sanitary Sewer Cleaning LF 3,885.000 3,864.000 $1.17 $4,520.88 2.3 8" Sanitary Sewer Cured -in -Place LF 3,885.000 3,864.000 $19.85 $76,700.40 2A 8"Hydrophilic End Seals Ea. 24.000 24.000 $125.00 $3,000.00 2.5 12" Hydrophilic End Seals Ea. 12.000 12.000 $135.00 $1,620.00 Change Order .Nn. I Value Completed .S4 1,328. 16 Total Value Completed - Bid Items sn'tt,a ):.84 Page 1 of 2 SUMMARY Original Contract I Total Complete Bid Item Subtotall $165,097.821 $58,899.68 APPROVED CHANGE ORDERS Change Order No. Description/Notes Total Approved Total Completed 1 8" CIPP Instead of to" CIPP and End Seals $2,871.75 $91,328.16 2 $0.00 $0.00 3 $0.00 $0.00 4 $0.00 $0.00 5 $0.00 moo 6 $0.00 $0.00 7 $0.00 $0.00 8 $o.00 $0.00 9 $0.00 $0.00 10 $0.001 $0.00 Total Change Orders $2,871.751 $91,328.16 Total Approved Total Completed Revised Contract Pricel $167,969.571 $150,227.84 Total Completed Total Materials Stored $0.00 - Total Completed Plus Materials Stored $150,227.84 Retains a (5%) $7,511.39 Total Earned Less Retainage $142,716A5 APPROVED PARTIAL PAYMENTS Partial Payment No. Period Total Approved 1 $131,428.58 2 $0.00 3 $0.00 4 $0.00 5 $0.00 6 $0.00 7 $0.00 8 $0.00 9 $0.00 10 $0.00 Total Previously Approved $131,428.58 Amount Due This Request $11,287.87 Note: The amount $11.267.87 is recommended for approval for payment in accordance with the terms of the Contract. CONTRACT SUMMARY ORIGINAL CONTRACT AMOUNT $165,097.82 TOTAL CONTRACT AMOUNT PLUS CHANGE ORDERS $167,969.57 THIS PARTIAL PAYMENT $11,287.87 TOTAL PARTIAL PAYMENTS INCL THIS PAYMENT $142,716.45 BALANCE $25,253.12 PERCENT COMPLETE 89 4% Recommended By. Veenstra & Kimm, Inc. Contractor. H dro-Klean LtC4 Approved. City of Waukee Signature Signature Si nature Name Sara Kappos Name ? e- OVOA/f Name Title Project Engineer Title V, e¢S/be Title Date c76 /& Date Date Page 2 of 2