HomeMy WebLinkAbout2016-07-05-J06 Enterprise Business Park Plat 6_PrelimPlat AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: July 5, 2016
AGENDA ITEM: Consideration of approval of a resolution approving a preliminary plat for
Enterprise Business Park Plat 6
FORMAT: Resolution
SYNOPSIS INCLUDING PRO & CON: Sundance, Inc. with property owner G.F. Land Partnership
requests approval of a preliminary plat in order to replat Lots 8 and 9 of
Enterprise Business Park Plat 2. The purpose of the replatting is to combine
the two lots into one 1.13 acre lot for the development of a Taco Bell fast food
restaurant.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT: The Planning and Zoning Commission
reviewed this request on June 28, 2016 and recommended approval subject to remaining
staff comments.
Approval of a Preliminary Plat for Enterprise Business Park Plat 6
Senior Planner Andy Kass introduced the proposal from the Applicant, Sundance, INC, and GF Land
Partnership, who have entered a request for a preliminary plat, final plat, and site plan approval for the
development of a Taco Bell restaurant. The Subject property is located at the corner of NE Carefree
Lane and Hickman Road. The area is 1.13 acres in area and is currently zoned C-1, Community and
Highway Service Commercial District. The Purpose of platting is to re-plat the two lots, initially
proposed in the 2nd plat of Enterprise Business Park, into one lot. The site plan identifies a 2500 square
foot restaurant with associated drive thru windows and menu boards. The required 39 parking lots are
being provided along with the introduction of some bicycle parking. Utilities will be connected to
existing stubs and there is a proposed 1000 gallon grease trap for the property. Storm water detention
will be directed to a large drain basin that was created during earlier plats of the area just north of NE
Venture Drive. There will be a connection off of the Raccoon River Valley Trail and NE Carefree
lane. The applicant has depicted a 34% open space dedication with the required trees shown on the
property as well as a berm on the east side and the dumpster located on the North West corner. Staff is
comfortable with the elevations utilizing a mix of brick, cement board, glazing, and metal paneling,
and recommend approval subject to remaining staff comments and review of the legal documents by
the city attorney.
Commissioner Streit questioned if any mechanical items would be roof mounted and Mr. Kass advised
that it will need to be screened if any mechanical aspects were roof mounted.
Commissioner Schmidt questioned if the storm water would be draining overland, and Mr. Kass
advised that it would all be piped underground to the existing pond.
Commissioner Schmidt Moved for Approval of a Preliminary Plat for Enterprise Business Park Plat 6
subject to remaining staff comments and review of the legal documents by the city attorney. Seconded
by Commissioner Fontenot. Ayes: Nigro, Fontenot, Streit, Hoifeldt, and Schmidt. Nays: None. Motion
Carries.
STAFF REVIEW AND COMMENT: At this time a majority of staff comments have been
addressed. Staff recommends approval subject to remaining staff comments.
RECOMMENDATION: Approve the resolution
ATTACHMENTS: I. Proposed Resolution
II. Staff Report
III. Staff Comment Letter
IV. Preliminary Plat/Site Plan (see Taco Bell Site Plan)
PREPARED BY: Andy Kass, Senior Planner
REVIEWED BY:
THE CITY OF WAUKEE, IOWA
RESOLUTION 16-
APPROVING THE ENTERPRISE BUSINESS PARK PLAT 6 PRELIMINARY PLAT
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Dallas County, State of Iowa, is a duly organized Municipal
Organization; AND,
WHEREAS, the City of Waukee Planning and Zoning Commission reviewed and recommended
approval of a Preliminary Plat for Enterprise Business Park Plat 6 on June 28, 2016, subject to
remaining staff comments; AND,
WHEREAS, the Preliminary Plat for Enterprise Business Park Plat 6 is in general conformance
with section §303 - Land Subdivision Ordinance of the Waukee Municipal Code.
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Waukee, Iowa on
this the 5th day of July, 2016, that the Preliminary Plat for Enterprise Business Park Plat 6 be
approved subject to remaining staff comments.
____________________________
William F. Peard, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
ROLL CALL VOTE AYE NAY ABSENT ABSTAIN
Brian Harrison
Shelly Hughes
Larry R. Lyon
Rick Peterson
VACANT SEAT
STAFF REPORT
TO: Planning and Zoning Commission PREPARED BY: Andy Kass
RE: Enterprise Business Park Plat 6 / Taco Bell –
Preliminary Plat, Final Plat, and Site Plan
DATE: June 28, 2016
GENERAL INFORMATION:
Applicant: Sundance, Inc. & G.F. Land Partnership
Requested Action
Preliminary Plat, Final Plat, & Site Plan Approval
Location and Size: Property is generally located west of NE Carefree Lane,
north of Hickman Road containing approximately 1.13
acres.
LAND USES AND ZONING:
Location Existing Land Use Comprehensive Plan Current Zoning
Property in Question Vacant – Undeveloped Neighborhood Residential C-1
North Goddard School – Under
Construction Neighborhood Residential C-1
South Commercial Neighborhood Residential C-1
East Commercial Neighborhood Residential C-1
West Light industrial Neighborhood Residential M-1
BACKGROUND:
The applicant is requesting approval of a preliminary plat, final plat, and site plan in order to develop a Taco
Bell fast food restaurant. The property is located in the northwest corner of the Hickman Road / NE Carefree
Lane intersection. The subject property was platted as two lots in Enterprise Business Park Plat 2 and the
platting request is to combine the two lots into one lot.
June 24, 2016
2 of 3
ABOVE: Aerial of subject property in relation to the surrounding area.
PROJECT DESCRIPTION:
The project involves the construction of an approximately 2,500 square feet Taco Bell restaurant and
associated parking and landscaped areas on property located at the intersection of Hickman Road and NE
Carefree Lane. The property is 1.13 acres in area and is currently configured as two separate lots. The
property is zoned C-1 Community & Highway Service Commercial District which allows for fast food
restaurants with drive-thru windows.
ACCESS AND PARKING:
Ingress and egress to the site will be provided via a driveway off of NE Carefree Lane located on the north
side of the site. The proposed use is required to have 39 parking spaces and the site plan identifies 29 parking
spaces being provided. An additional 5 queuing spaces per drive-thru lane are required for which the site plan
identifies compliance with this requirement. Pedestrian access to the site will be provided from the sidewalk
along NE Carefree Lane or from the proposed connection to the Raccoon River Valley Trail along Hickman
Road. The site plan also identifies bicycle parking spaces on the north side of the building.
UTILITIES:
All utilities have been extended to the site with Enterprise Business Park Plat 2. The applicant will connect t
the existing sanitary sewer and water service stubs. The utility plan identifies a 1,000 gallon grease trap
connected to the wastewater system. Storm water detention will be provided in the existing detention facility
that was constructed as part of the initial phases of Enterprise Business Park. This pond is located north of NE
Venture Drive. Storm water from the site will be directed to this pond.
June 24, 2016
3 of 3
LANDSCAPING:
The site plan identifies the appropriate number of plantings required by the Landscaping and Open Space
Ordinance. A minimum of 20% open space is required and the plan set identifies 34% open space.
ELEVATIONS:
The proposed apartment buildings will be constructed with brick veneer, fiber cement board, glazing, and
metal paneling. The colored elevations identify the location of a wall mural on the east side of the building and
the propose color scheme of brown, white, and bronze.
STAFF RECOMMENDATION
At this time Staff is comfortable with the preliminary plat/site plan and final plat and would recommend
approval of the preliminary plat/site plan and final plat subject to remaining staff comments and review of all
legal documents by the City Attorney.
CITY OF WAUKEE
Andy Kass, AICP
Senior Planner
Development Services Department
230 W. Hickman Road
Waukee, IA 50263
Phone: (515) 978-9533
Fax: (515) 987-1845
1st Review: May 24, 2016
2nd Review: June 7, 2016
3rd Review: June 29, 2016
4th Review:
Excel Engineering
Attn: Jason Daye
100 Camelot Drive
Fond Du Lac, WI 54935
RE: Taco Bell – Site Plan
Dear Mr. Daye:
Per your request, staff has reviewed the proposed site plan for Taco Bell. The property is located at the
northwest corner of Carefree Ln and Hickman Rd. Based upon our review, staff has the following comments
related to the site plan:
COVER SHEET & GENERAL COMMENTS
1. Provide project manager contact information on the cover sheet.
Engineers Response:
2. Provide the legal description on the cover sheet.
Engineers Response:
3. A final plat should be submitted as part of the next submittal.
Engineers Response:
4. Provide the property address on the cover sheet (40 NE Carefree Lane).
Engineers Response:
5. Please provide a materials board with the next submittal.
Engineers Response:
6. Please revise label for Carefree Lane to “NE Carefree Lane” on all sheets of the plan set.
Engineers Response:
7. A note should be added to the plan set indicating that all City of Waukee Standard Specifications for
Public Improvements and the most recent edition of SIDAS Standard Specifications, if applicable, shall
apply to all work on this project unless otherwise noted.
Engineers Response:
Project Name Project Engineer/Manager Project Type City Contact
Taco Bell Jason Daye Site Plan Andy Kass
8. A note should be added to the plan set indicating that all construction within City right-of-way,
easements, or any connection to public utilities the contractor shall notify the City of Waukee
Engineering Department one week prior to contruction.
Engineers Response:
9. A note should be added to the plan set indicating that any changes proposed to the plan set during
construction shall receive written approval from the Waukee Development Services Department.
Engineers Response:
10. A note should be added to the plan set indicating that the contractor is responsible for any changes
made during construction that have not been granted approval in writing from the Waukee
Development Services Department.
Engineers Response:
11. A note should be added to the plan set indicating that the contractor is responsible for replacing any
areas of pavement or sidewalk not to be removed that is damaged due to operating equipment on the
pavement or sidewalk. Pavement replacement shall comply with Waukee Standard Specifications for
Public Improvements.
Engineers Response:
12. A note should be added to the plan set indicating any proposed building or monument signage will
require a sign permit and are to be reviewed and approved by the Waukee Development Services
Department.
Engineers Response:
13. A note should be added to the plan set indicating that all construction staking including pedestrian
facilities shall be completed under the direction of a licensed engineer or land surveyor.
Engineers Response:
14. A note should be added to the plan set indicating that the contractor is responsible for setting up a pre-
construction meeting with the Waukee Development Services Department 1 week prior to
construction activities commencing.
Engineers Response:
15. A note should be added to the plan set indicating that the contractor is responsible for notifying the
Waukee Development Services Department of any planned weekend or holiday work 48 hour prior to
said work commencing.
Engineers Response:
16. A note should be added to the plan set indicating that all offsite established lawns disturbed by
construction activities shall be replaced with sod and watered until established.
Engineers Response:
17. Notes A, E, and F and each sub note in Section 31 30 00 should reference controls in SUDAS
Specifications section 9040.
Engineers Response:
18. Note F.8 under Section 31 30 00 Erosion Control, should include that concrete washout will be lined
with plastic.
Engineers Response:
19. Note F.11 under Section 31 30 00 Erosion Control, should include that in addition to “be cleaned up by
the end of each working day, and prior to a rain event”.
Engineers Response:
20. Note C & D under Section 31 30 00 Erosion Control, rain inspections are no longer required by
General Permit #2 and this reference and this reference can be removed if the will not be required for
the site.
Engineers Response:
21. Note D under Section 31 30 00 Erosion Control, staff questions if this should be for sediment controls.
Please address.
Engineers Response:
22. Note C under Section 31 30 00 Erosion Control, the local permit required by Waukee is a COSESCO
permit (Construction Site Erosion and Sediment Control ordinance).
Engineers Response:
23. Note D.3 under Division 32 should be revised to 8-inch PCC in the right-of-way.
Engineers Response:
24. Note E under Division 32 should state tha all concrete in the right-of-way is to be C-4 mix.
Engineers Response:
25. Notes A & B under Section 32 30 00 should reference that it will met General Permit #2 requirement
for topsoil and not include a numeric value.
Engineers Response:
26. Note B under Division 33 should call for SDR 23.5 PVC.
Engineers Response:
27. Note C under Division 33 should provide a detail of the cleanout referenced.
Engineers Response:
28. Note I under Division 33 should reference the Waukee Standard Specifications for Public Improvements
prior to SUDAS.
Engineers Response:
29. Please reorder the numbering/lettering under Plan Specifications section 31.30.00 Erosion
Control (see the last three – C, D, and E).
30. Please verify ownership information as the Assessor’s records show GF Land Partnership
as the owner.
31. Change legal description to read “Enterprise Business Park Plat 6 Lot 1” to correspond to
what the Plat will be named after replatting.
32. If the applicant would like to have an address off of Hickman Road an address of 95 East
Hickman Road can be used.
SHEET C1.1EX | EXISTING SITE AND DEMOLITION PLAN
33. Adjust note to state to grind or cut curb as needed for a SUDAS Type A driveway.
34. The existing water on the east side of NE Carefree Lane is 8-inch and the storm on the west side is 21-
inch.
SHEET C1.2SP | SITE PLAN
35. Indicate warning panels on the curb ramps within the right-of-way along NE Carefree Lane as well as the
pedestrian crossing located on the south side of the site.
Engineers Response:
36. Label existing easements with book and page numbers. Label recorded book and page number for
the street easement.
37. Label building square footage on the plan.
38. Staff suggests using 7” pavement for this site.
39. Please revise “Minimum Landscaping Area” under the Site Information block to “Minimum Open Space
Area”.
40. Staff suggests providing bicycle parking on this site.
41. Staff questions if an outdoor patio is proposed. If so, please provide details. Include any details of fencing
if fencing is being proposed.
42. Provide a downspout connection detail and label these locations on the site plan.
43. Add a note that the driveway thickness if 8-inch PCC in the right-of-way.
44. Add to the SUDAS Type A Driveway note “with radii”.
45. Staff suggest providing a sidewalk into the site from NE Carefree Lane.
46. Remove the pavement markings from the driveway entrance to the site.
47. The site plan should reference the 5 queuing space requirement per drive-thru window and
demonstrate compliance with that requirement.
Engineers Response:
SHEET C1.3GE | GRADING AND EROSION CONTROL PLAN
48. Demonstrate grades meet 2% slope in all unpaved areas. Demonstrate this on the east side of the
site.
49. Provide proposed location(s) for the following
a. Topsoil stockpile
b. Staging/materials area
c. Waste containment – concrete washout, sanitary waste, construction debris
d. Provide notes/illustrate final discharge locations and name of ultimate receiving waterbody.
50. Provide pedestrian facility information for ramps (running ramp grades, spot elevations, cross slope,
etc.). Information specific to each ramp should be provided for those within the right-of-
way.
Engineers Response:
51. Please indicate the cross slope of the trail at the tie-in for the sidewalk along NE Carefree
Lane.
52. Call out the location of the concrete flume.
SHEET C1.4UT | UTILITY PLAN
53. The storm sewer pipe within the right-of-way needs to be 15” RCP minimum. Please revise to be
RCP rather than HDPE.
54. Label all critical crossings with top and bottom of pipe elevations.
55. Label size of pipes for all utilities shown.
56. Show hydrant radius coverage.
57. Separate the water (domestic and fire) on the outside of the building and provide a valve for each after
the separation
58. Verify if a major manhole adjustment is required (due to elevation change) for the existing storm
manhole that is proposed for the driveway.
59. The hydrant radius coverage should be 150’ rather than 100’. Please revise.
60. Staff questions if the 1,000 gallon grease interceptor is adequate for the proposed use.
SHEET C1.5LA | LANDSCAPE PLAN
61. Provide the open space calculation – amount required and amount provided.
62. Please provide one tree per 40 lineal feet within the parking setback.
63. Please provide a 3’ berm on both the south and east sides of the site, if feasible.
64. Add the parking lot setback requirement of one tree per 40 lineal feet under the
landscaping calculations tab.
65. Add a note indicating that all disturbed areas onsite are to be replaced with sod.
Engineers Response:
SHEET C1.6LT1 | SITE LIGHTING PHOTOMETRIC PLAN
66. In the statistics box, please revise the max allowed to 10 foot candles, rather than the 11 fc shown.
SHEET C1.7LT2 | SITE LIGHTING PHOTOMETRIC PLAN
67. Provide the lumens for the first light fixture shown on this sheet.
68. Please indicate whether the LED 2 Series and Ecoform fixtures are full cut off fixtures.
SHEET C1.8DT1 | SITE DEVELOPMENT DETAILS
69. Staff questions if the concrete flume detail is applicable to this project. Please address.
SHEET C1.9DT2 | TACO BELL CORPORATE DETAILS
70. Please indicate if the monument sign is proposed to be double sided.
71. Staff questions if the brick proposed for the base of the monument sign is similar to what is proposed
for the building.
SHEET A4.2 | COLOR ELEVATIONS
72. On the Walk-up Elevation, provide a mix of building materials in order to break up the mortarless
concrete brick veneer.
Engineers Response:
73. Staff questions if an alternate color or a mix of colors on the brick could be used.
Engineers Response:
74. Provide a mixture of building materials on the rear elevation in order to break up the white brick. The
site plan ordinance requires that long expanses of wall be broken up by utilizing a mix of materials or
other architectural treatments.
Engineers Response:
75. Provide a mixture of building materials on the drive-thru elevation in order to break up the white brick
proposed. The site plan ordinance requires that long expanses of wall be broken up by utilizing a mix of
materials or other architectural treatments.
Engineers Response:
76. Provide an example of the mural.
Engineers Response:
77. Staff questions if roof mounted mechanical units will be utilized for the proposed building.
If so, architectural screening will be required per the site plan ordinance. The screening
should be identified on the elevations.
Engineers Response:
VEENSTRA & KIMM COMMENTS:
78. Show estimated number of employees.
79. Add a note stating the contractor is responsible to set up a preconstruction meeting.
80. Provide geotechnical report. Add a note to the plan set indicating that the results of the report are to
be provided to the City of Waukee Engineering Department and the plan set is subject to any changes
required by the report.
81. Add a note stating the contractor shall notify the City of Waukee Engineering Department 48 hours
prior to the beginning of construction and prior to any weekend or holiday work.
82. Add a note indicating that the contractor shall provide submittals of construction materials prior to
construction.
83. Add a note indicating any changes proposed to the plan set during construction to receive written
approval from the City of Waukee Engineering Department. The note should also indicate that the
contractor is responsible for any changes made during construction that have not received written
permission from the City of Waukee Engineering Department.
84. Add a note stating that curb ramps are to be staked by a licensed engineer.
85. Add a note stating that as-builts should be provided to the City of Waukee Engineering Department.
86. Add a note stating that testing is to be completed per City of Waukee Specifications and that all tests
are to be witnessed by the City.
87. Show spot elevations and slope information for all pedestrian crossings. Show cross slope grades on
crosswalks through driveway and parking lot. Sidewalk cross slope exceeds 2% at sidewalk next
to building and at sidewalk along NE Carefree Lane. Please adjust. Show additional spot
elevations at curb ramp near drive-thru. Some spot elevations at curb ramps are not
shown at the bottom corners of ramps. Please move to correct locations. Show slope
information at curb ramps where slope does not match the 1:12 running slope and/or 2%
cross slope indicated. Show cross slope grades on crosswalks through driveway and
parking lot. Show detectable warning panels matching full width of sidewalk.
Engineers Response:
88. Show spot elevations and slope information for existing trail at the connection points of new sidewalks.
Modify the existing trail if ADA and PROWAG guidelines cannot be met at these locations.
89. Modify northern catch basin invert elevations to provide minimum of 0.1’ of fall through the structure.
90. Modify storm sewer size located within public right-of-way to minimum of 15” diameter. Change 15”
storm sewer within public right-of-way to RCP instead of HDPE. Modify corresponding
invert size on upstream and downstream structures.
Engineers Response:
91. Show critical crossing information including top and bottom of pipe elevations for crossing of storm
sewer and sanitary sewer at northeast corner of site.
92. Storm Water Calculation:
a. Indicate and illustrate 100-year flood elevation and overflow route.
b. Correct Basin 3 drainage area on Storm Basin Map.
c. Provide Hydrograph Reports for Basins 2 and 3.
d. Correct drainage area in Hydrograph No. 1.
e. Storm Basin Map, Existing Site Map, and Post Construction BMP’s are upside down. Please
correct.
f. Storm Water Calculation: Correct drainage area in Hydrograph No. 1 to
correspond with area shown on Storm Basin Map.
Engineers Response:
FIRE DEPARTMENT COMMENTS
93. Construction sequence - Construction Site Access per 1401.1.1, other than installation of underground
utilities and non-combustible foundations. Access roads to buildings or structures shall be constructed
no further away than 50 feet from the building or structure with the middle of the building or structure
no further than 150 feet from the access road.
Engineers Response:
94. C1.2SP West lane of main parking on south side, width need to maintain 20 width for fire apparatus
access per section 503.
Engineers Response:
95. Proposed Fire hydrant is within approximate distance from FDC. The hydrant can be moved to center
island as would require less piping and would be easier for our access. We would not be planning on
using the road being the building as it currently is not the required width.
Engineers Response:
96. Per municipal code of The City of Waukee, two fire apparatus accesses are required for all commercial
properties. At this time, the single access will be allowed since the building has automatic fire sprinklers
and the current site will not allow a second access point. If there is any change to the adjacent property
to the west where would allow the ability for an additional access then it will be required at that time.
Engineers Response:
97. A1.0 Sprinkler riser shall be separated from electrical room as per 903.3.5.3.
Engineers Response:
98. A4.2 sprinkler room and fire alarm room signage shall be installed on the door it serves.
Engineers Response:
99. Knox box installed at front entrance on the right side of the door at the height of 6 feet at the top of
the box from the ground.
Engineers Response:
100. Steamer connection of Hydrant will face north. Maintain 5 foot clearance for
landscaping from hydrant.
101. Provide identification of all equipment in rider room.
FINAL PLAT
102. Provide the book and page number for the 15 foot street easement indicated.
103. The legal description should reference Lots 8 and 9 on Enterprise Business Park
Plat 2, not Plat 6.
104. Carefree Lane should be indicated as NE Carefree Lane.
105. Provide the book and page number for the 15 foot street easement indicated.
106. The provided final plat does not scale out correctly.
107. The address for the property should be indicated as 40 NE Carefree Lane.
Alternatively an address of 95 East Hickman Road can be used.
108. Verify that all proposed easements are indicated on the final plat.
109. Bulk regulations for the C-1 zoning district should be indicated on the final plat.
110. Staff questions if the owner is the applicant or if the Taco Bell developer is also the
applicant. If so, please indicate the applicants name and contact information.
111. All legal documents related to platting should be submitted for review by the City
Attorney. Until legal documents are submitted this plat will not be forwarded to the City
Council for approval.
Engineers Response:
112. A check in the amount of $250.00 should be submitted to satisfy the final plat
review fee.
MISCELLANEOUS COMMENTS:
113. Provide a copy of the Construction Site SWPPP Review Checklist signed by the SWPP designer.
Engineers Response:
114. Provide a copy of the SWPPP Prepared for obtaining General Permit #2 coverage.
Engineers Response:
115. Provide a copy of the IDNR issued General Permit #2 authorization letter.
Engineers Response:
116. Submit $65 fee for the first required quarterly COSESCO inspection.
Engineers Response:
The applicant will be required to provide the following as a part of the completion of the public improvements
prior to approval of a final plat:
117. Post Construction What practices considered for this site?
118. Provide a site plan specific to the storm water management facilities of the property indicating
the permanent measures utilized by the designer and requirements for maintenance of said facilities.
119. A maintenance covenant will need to be created and provided for review (if different than the
existing).
120. As-built plans of all storm water management facilities on site and a certification statement
signed by SWPPP designer indicating that facilities were constructed as designed will be required.
Staff would request that the revised plans and comment response letter be provided in digital form (PDF) and
hard copies with 5 full-sized hard copies delievered to Waukee City Hall. The PDF copy may be emailed. One
additional hard copy set including any storm water management materials should be delivered directly to
Veenstra and Kimm to Jordan Kappos’ attention.