CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 1, 2016
AGENDA ITEM: Consideration of approval of Change Order No. 2 to J&K Contracting for
the Bluestem Lift Station No. 14 Improvement Project, decreasing the
total contract price in the amount of $3,630.00
FORMAT: Consent Agenda
SYNOPSIS INCLUDING PRO & CON: The Change Order includes the following:
Modifications to Premanufactured Control Building
Modifications to the access Drive and Gate
Addition of Temporary Irrigation
Removal of Sanitary Sewer Stub
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $3,360.00 contract
dedcut
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. McClure Engineering Letter of Recommendation
II. Change Order No. 2
PREPARED BY: John Gibson