HomeMy WebLinkAbout2016-12-19-J01L RRVT Trailhead Public Art_Pmt Est 1 AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: December 19, 2016
AGENDA ITEM: Consideration of approval of Payment Estimate No. 1 to RDG Dahlquist Art
Studio, for the Raccoon River Valley Trailhead Public Art Project in the
amount of $49,892.75.
FORMAT: Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Payment Estimate No. 1 to RDG Dahlquist Art Studio is
for purchasing of steel for the pergola and plaza canopy and concrete. The
designer is currently completing mock-up bollards to determine the best
installation of the clay tile. It is anticipated that they will have mock-ups for
staff to see by mid January. Construction of the concrete bollards and the
pergola structure will begin in the spring. Prepping the clay tile takes
approximately 5-6 months. The quantities completed to date have been
reviewed and agreed upon by the contractor, City of Waukee Staff.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Payment Estimate No. 1
PREPARED BY: Matt Jermier
REVIEWED BY: