CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 2, 2021
AGENDA ITEM:Consideration of approval of Change Order No. 1 to Elder Corporation
for the NW Douglas Parkway – NW 10th Street to NW 2nd Street Project
increasing the contract amount by $77,829.90.
FORMAT:Motion
SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 is for additional subgrade prep,
storm sewer, subdrain, pavement, sidewalk, and driveway to coordinate with adjacent
development.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $77,829.90. The City will receive a
partial reimbursement of $67,307.90 from the adjacent developer, Temple Holdings/Courtyards at
Parkside LLC, at the time of final plat.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 1
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J6
8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393
July 20, 2021
Rudy Koester, P.E.
Public Works Director
805 University Avenue
Waukee, IA 50263
RE: Change Order #1
NW Douglas Parkway - NW 10th Street to NW 2nd Street
Dear Mr. Koester:
Attached please find a detailed Change Order for City Council approval on August 2, 2021.
Change Description:
Item 2.4 Subgrade Preparation, 12 in.
o Increased contract quantity to coordinate with adjacent development.
Item 2.5 Subbase, Modified, 6 in.
o Increased contract quantity to coordinate with adjacent development.
Item CO 2.6 Removal of pipe culvert less than or equal to 6 in.
o Added contract quantity to coordinate with adjacent development.
Item 4.4 Storm Sewer, Trenched, RCP, Class V, 15 in.
o Increased contract quantity to coordinate with adjacent development.
Item 4.9 Subdrain, PVC, 6 in.
o Increased contract quantity to coordinate with adjacent development.
Item 4.10 Subdrain Cleanout, Type A-1
o Increased contract quantity to coordinate with adjacent development.
Item 4.11 Subdrain, Outlet, Connection to Intake
o Increased contract quantity to coordinate with adjacent development.
Item 6.3 Intake, SW-505, Double Grate
o Increased contract quantity to coordinate with adjacent development.
Item 7.1 Pavement, PCC, Class C-SUD, 10 in.
o Increased contract quantity to coordinate with adjacent development.
Item 7.8 Sidewalk, PCC, 6 in.
o Increased contract quantity to coordinate with adjacent development.
Item 7.9 Detectable Warning
o Increased contract quantity to coordinate with adjacent development.
Item 7.10 Driveway, PCC, 8 in.
o Increased contract quantity to coordinate with adjacent development.
We have reviewed the submitted quotes from Elder Corporation and they appear to be in order
with current industry pricing. If City Staff concurs with this pricing, we recommend the City of
C:\pw_workdir\pw_ie\fvd_amw2\d0520131\Ltr_2021-0720_Waukee-NW Douglas Parkway-Recommend CO1.docx
Waukee Increase the contract price in the amount of $77,829.90 to complete the additional work
associated with Change Order #1. If you have any questions, please contact me.
Sincerely,
Foth Infrastructure & Environment, LLC
Andy Floy, P.E.
Lead Civil Engineer
Encl: Change Order #1 dated 7/22/2021
CHANGE ORDER 01
Distribution:
Owner - Finance ____
Owner - Public Works ____
Engineer ____
Contractor ____
Contractor:Elder Corporation
5088 East University Ave.
Des Moines, Iowa 50327 $1,854,767.50 December 22, 2020
2.4 SY $2.40 842 $2,020.80
2.5 SY $6.30 842 $5,304.60
CO 2.6 LF $38.50 172 $6,622.00
4.4 LF $50.00 78 $3,900.00
4.9 LF $15.50 277 $4,293.50
4.10 EA $510.00 3 $1,530.00
4.11 EA $245.00 4 $980.00
6.3 EA $3,500.00 1 $3,500.00
7.1 SY $56.50 676 $38,194.00
7.8 SY $50.00 50 $2,500.00
7.9 SF $50.00 40 $2,000.00
7.10 SY $55.00 127.00 $6,985.00
$77,829.90
$1,854,767.50
$0.00
$1,854,767.50
$77,829.90
$1,932,597.40
0 Days
Recommended By:
Elder Corporation
Signature:
Name: Nick Tometich
Title: Project Manager
Date:
Owner:City of Waukee
□ ≤$500 Department Director X_______________________________________Date___________________
□ $501 to $2,500 City Administrator X_______________________________________Date___________________
□ Date___________________
□ >$2,501 City Council approved or ratified at Council meeting on Date___________________
THE CONTRACT IS CHANGED AS FOLLOWS: Due to adjacent development and coordination between projects, intersection paving and pedestrian ramps will be added along NW
Douglas at 322+24. This includes a new intake, storm sewer and subdrain. Also included is removal of 172' of 30" RCP storm sewer and modification to existing structures with an
addition of a 15" RCP stub across Douglas. This is all categorized under Division 2.
DETECTABLE WARNING
Item Code
Department of Public Works
805 University Avenue
Waukee, IA 50263
(515) 987-7920 Fax (515) 987-3979
Project Title
July 20, 2021
Foth Project File Number
Orig. Contract Amount & Date
Date
Change Order Number
NW Douglas Parkway
NW 10th Street to NW 2nd Street
1
19W029.01
Waukee Project File Number
6010-B-1505
Description
INTAKE, SW-505, DOUBLE GRATE
Foth Infrastructure & Environment, LLC
The Contract Sum prior to This Change Order was
UnitItem No.
7030-G-1000
4020-A-1515 STORM SEWER, TRENCHED, RCP, CLASS V, 15 IN.
Date:
The Contract Time will be increased by
CHANGE ORDER SUMMARY
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
The Original Contract Sum was
City of Waukee
Net Change by previously authorized Change Orders
Title: City Administrator
4040-A-1106
Name: Andy Floy, P.E.
Date:
Name: Tim Moerman
Checked By: Prepared By:
Title: Lead Civil Engineer
Signature:
The Contract Sum will be increased by this Change Order in the amount of
Value Adjustment
The new Contract Sum including this Change Order will be
Signature:
Quantity
AdjustmentUnit Price
SUBDRAIN, PVC, 6 IN.
4040-D-1000 SUBDRAIN, OUTLET, CONNECTION TO INTAKE
4040-C-1000 SUBDRAIN CLEANOUT, TYPE A-1
DRIVEWAY, PCC, 8 IN.7030-H-1008
7010-A-1010 PAVEMENT, PCC, CLASS C-SUD, 10 IN.
7030-E-1006 SIDEWALK, PCC, 6 IN.
2010-I-1006 SUBBASE, MODIFIED, 6 IN.
2010-J-2200 REMOVAL OF PIPE CULVERT LESS THAN OR EQUAL TO 36IN.
2010-G-1012 SUBGRADE PREPARATION, 12 IN.
CO#01-2021-0720-NW Douglas Parkway Construction.xls Change Order 1 Page 1 of 1