CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 16, 2021
AGENDA ITEM:Consideration of approval of Change Order No. 3 to Absolute Concrete
Construction, Inc. for the NW 10th Street Improvements, W Hickman
Road to NW Douglas Parkway increasing the contract price in the
amount of $28,964.23.
FORMAT:Motion
SYNOPSIS INCLUDING PRO & CON: Change Order No. 3 is for additional grading for the
temporary granular access, insulation over the existing water main, lowering a section of water
main, and pedestrian pushbuttons.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $28,964.23. Of this total change
order amount, Foth will be reimbursing the City $20,653.22 (item CO 3.2) due to a design error.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Motion to Approve.
ATTACHMENTS: I. Change Order No. 3
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1Q
8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 Fax: (515) 254-1642
August 3, 2021
Sara Kappos, P.E.
Assistant Director of Public Works
805 University Avenue
Waukee, IA 50263
RE: Change Order #3
NW 10th Street Improvements
W Hickman Rd to NW Douglas Parkway
Dear Ms. Kappos:
Attached please find a detailed Change Order for City Council approval on August 16, 2021.
Change Description
Item 2.4 Excavation, Class 10, Roadway & Borrow
o Increase item for extra grading for temporary access to the Stratford Development.
Item CO 3.1 Insulation of Water Main
o Add item for insulation over shallow main along NW 10th Street.
Item CO 3.2 Time and Material for Lowering Water Main in SE Corner of Sunrise and NW 10th.
o Add item for main lowering to minimum 5 ’ bury.
Item CO 3.3 APS Pedestrian Pushbuttons
o City requested additional pushbuttons in SE corner of Hickman and 10th.
We have reviewed the submitted quotes from Absolute Concrete Construction, Inc. and they appear to be
in order with current industry pricing. If City Staff concurs with this pricing, we recommend the City of
Waukee Increase the contract price in the amount of $28,964.23 to complete the additional work
associated with Change Order #03.
Please let me know if you have any questions or need additional information.
Sincerely,
Foth Infrastructure and Environment, LLC
Joshua C. DeBower, P.E.
Lead Civil Engineer
Encl: Change Order #3 dated 08/03/2021
CHANGE ORDER 03
Distribution:
Owner - Finance ____
Owner - Public Works ____
Engineer ____
Contractor ____
Contractor:Absolute Concrete Construction, Inc.
1000 West 6th Avenue
PO Box 148 $9,845,649.70 November 5, 2019
Slater, Iowa 50244
2.4 CY $3.50 750 $2,625.00
CO 3.1 LS $3,376.01 1 $3,376.01
CO 3.2 LS $20,653.22 1 $20,653.22
CO 3.3 EA $1,155.00 2 $2,310.00
$28,964.23
$9,845,649.70
$152,906.10
$9,998,555.80
$28,964.23
$10,027,520.03
0 Days
Recommended By:
Absolute Concrete Construction, Inc.
Signature:
Name: Logan Petersen
Title: Project Manager
Date:
Owner:City of Waukee
□ ≤$500 Department Director X_______________________________________Date___________________
□ $501 to $2,500 City Administrator X_______________________________________Date___________________
□ Date___________________
□ >$2,501 City Council approved or ratified at Council meeting on Date___________________
3
Title: Lead Civil Engineer
Signature:
The Contract Sum will be increased by this Change Order in the amount of
Net Change by previously authorized Change Orders
Title: City Administrator
Value Adjustment
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Foth Infrastructure & Environment, LLC
The Contract Sum prior to This Change Order was
Signature:
Name: Joshua C. DeBower, P.E.
Date:
Name: Tim Moerman
Checked By: Prepared By:
THE CONTRACT IS CHANGED AS FOLLOWS: Increase quantity for extra grading for temporary access to the Stratford Development, addition of time and materials for insulation
over 12" water main, addition of time and materials for water main lowering in the SE corner of Sunrise and 10th and addition of two APS pushbuttons per city request in the SE
corner of Hickman and 10th.
Unit
The new Contract Sum including this Change Order will be
Special TIME AND MATERIAL FOR LOWERING WATER MAIN IN SE CORNER OF SUNRISE
AND NW 10TH
2010-E-1010
Date:
The Contract Time will be increased by
CHANGE ORDER SUMMARY
Item No.Quantity
AdjustmentUnit Price
Special APS PEDESTRIAN PUSHBUTTONS
The Original Contract Sum was
City of Waukee
Department of Public Works
805 University Avenue
Waukee, IA 50263
(515) 987-7920 Fax (515) 987-3979
Special
Description
Project Title
Waukee Project File Number
Item Code
EXCAVATION, CLASS 10, ROADWAY & BORROW
Change Order Number
NW 10th Street Improvements
W. Hickman Road to NW Douglas Parkway
INSULATION OF WATER MAIN
19W003.00
August 3, 2021
Foth Project File Number
Orig. Contract Amount & Date
Date
CO#03-2021-0731-NW 10th Street Improvements.xls Change Order 1 Page 1 of 1