HomeMy WebLinkAbout2021-09-07-J01R Ute Ave-Ashworth Rd Intersection_Professional Svcs Agr, Supplemental 2AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: September 7, 2021
AGENDA ITEM:Consideration of approval of a resolution approving Supplemental Agreement
for Additional Services No. 2 with Snyder & Associates, Inc. [Ute Avenue &
Ashworth Road Intersection Improvement Project]
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON: The original agreement was approved by City Council on
August 3, 2020 which included the preliminary and final design for widening and partial
reconstruction of the Ute Avenue and Ashworth Road intersection to provide adequate through and
right/left turn movements. New traffic signalization design is included as part of the project. The
project will support the increasing traffic generated by the continued growth and development of the
southwest portion of Waukee, including construction of the new Sugar Creek Elementary school.
Supplemental Agreement No. 1 was approved by City Council on June 21, 2021. Throughout the
course of design, the project has evolved to include scope of work that was not anticipated during the
initial contract development. The Consultant attempted to offset the increased cost by efficiencies in
other design tasks to maintain current budget. The Consultant was not able to fully offset the increased
scope and therefore respectfully requested a supplemental agreement.
Supplemental Agreement No. 2 comes after completion of design and bidding services, further
coordination took place between City staff and the Hamilton Ridge developer. This coordination
resulted in a request to revise a portion of Ashworth Road design from a rural section to an urban
section near the west project limits, station 118+36 to station 125+30. An urban section will require re-
design of the grading and roadway typical section, revised water main design, added storm sewer and
issuance of a design revision to the Contractor.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: Amendment No. 2 is for an
additional amount not to exceed $26,100.00. This amendment will bring the new contract amount to
$471,300.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the Supplemental Agreement for Additional Services No. 2
ATTACHMENTS: I. Resolution
II. Supplemental Agreement for Additional Services No. 2
PREPARED BY: Beth Richardson
REVIEWED BY: Rudy Koester RK
J1R
THE CITY OF WAUKEE, IOWA
RESOLUTION 2021
APPROVING SUPPLEMENTAL AGREEMENT FOR ADDITIONAL SERVICES NO. 2
WITH SNYDER & ASSOCIATES, INC. [UTE AVENUE & ASHWORTH ROAD
INTERSECTION IMPROVEMENT PROJECT]
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Iowa is a duly organized municipality within Dallas County;
AND,
WHEREAS, on August 3, 2020 (Resolution #2020-292), the Waukee City Council approved an
agreement with Snyder & Associates for Professional Consulting Services related to the Ute
Avenue and Ashworth Road Intersection Improvement Project; AND,
WHEREAS, on June 21, 2021 (Resolution #2021-274), the Waukee City Council approved a
Supplemental Agreement No. 1 with Snyder & Associates for Professional Consulting Services
related to the Ute Avenue and Ashworth Road Intersection Improvement Project; AND,
WHEREAS, following completion of design and bidding, further coordination took place
between City staff and the Hamilton Ridge developer. This coordination resulted in a request to
revise a portion of Ashworth Road design from a rural section to an urban section near the west
project limits, station 118-36 and 125+30. An urban section will require re-design of the grading
and roadway typical section, revised water main design, added storm sewer and issuance of a
design revision to the Contractor.
NOW THEREFORE BE IT RESOLVED by the City of Waukee City Council in session this
7th day of September, 2021, that it hereby approves the Supplemental Agreement for Additional
Services No. 2 with Snyder & Associates [Ute Avenue & Ashworth Road Intersection
Improvements Project].
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
ROLL CALL VOTE AYE NAY ABSENT ABSTAIN
Anna Bergman Pierce
R. Charles Bottenberg
Chris Crone
Larry R. Lyon
Ben Sinclair
SUPPLEMENT AL AGREEMENT FOR ADDITIONAL SERVICES # -02
To: Snyder & Associates, Inc.
2727 SW Snyder Blvd.
Ankeny, IA 50023
Attn: Nathan Carhoff
Phone: 5al5-964-2020
Fax: 5al5-964-7938
This is authorization for Snyder & Associates, Inc. to proceed with the following described additional services.
Client: City of Waukee
Project Name: Ute Avenue & Ashworth Road Intersection Improvement Project
S&A Project Number: 120.0783.0al I10riginal Agreement Date: August 3, 2020
DESCRIPTION OF ADDITIONAL SERVICES:
Refer to Attachment 1 B.
0 Lump Sum in the amount of: $
[Q Hourly plus expenses per original agreement or attached fee schedule, not to exceed budget: $26,100
[1 Document attached:
The undersigned, on behalf of the Client, understands and agrees that the services described in this
Supplemental are additional services, scope of which is not contained within the original scope of services
defined in the original agreement. The Additional Services in this Supplemental are subject to the general
conditions contained in the original Professional Services Agreement.
City of Waukee
(Type or Print Name above line)
By:
(Authorized Agent)
Courtney Clarke, Mayor
(Printed or typed signature)
Date:
(Client)SNYDER & ASSOCIATES, INC. (Professional)
By:
(Authorized Agent)
Mark A. Land, Vice President
(Printed or typed signature)
Date:DE>}z;>};mz)
Route executed to: Nathan Carhoff
Rev 04-1 6-19
V:lProjectsl2020l1 20.0783.OMdministratiorMgmt2021-08-1 3SAO2.docm
Page 1 of 1
-1-
V:\Projects\2020\120.0783.01\Administration\Agmt_2021-08-13_SA02Scope.docx
ATTACHMENT 1B
UTE AVENUE & ASHWORTH ROAD INTERSECTION IMPROVEMENT PROJECT
WAUKEE, IOWA
CLIENT: CITY OF WAUKEE
230 W. HICKMAN ROAD
WAUKEE, IOWA, ZIPCODE
C/O RUDY KOESTER
Hereinafter referred to as the “City”
ENGINEER: SNYDER & ASSOCIATES, INC.
2727 SW SNYDER BLVD
ANKENY, IOWA 50023
Hereinafter referred to as the “Consultant”
PROJECT: UTE AVENUE & ASHWORTH ROAD INTERSECTION IMPROVEMENT PROJECT
DATE: AUGUST 13, 2021
SCOPE OF SERVICES:
I. GENERAL
Following completion of design and bidding, it is understood further coordination took place between
City staff and the Hamilton Ridge developer. This coordination resulted in a request to revise a portion of
Ashworth Road design from a rural section to an urban section near the west project limits, station
118+36 to station 125+30. An urban section will require re-design of the grading and roadway typical
section, revised water main design, added storm sewer and issuance of a design revision to the Contractor.
Original contract scope of work did not include attendance of periodic construction meetings. It has been
requested that the Consultant attend bi-weekly construction meeting throughout the project.
This supplemental agreement request covers the additional design and construction service efforts
requested.
II. DESIGN
The Consultant will perform the following tasks related to the re-designed section.
A. Revise typical sections to remove granular shoulder, add a 3.5-foot curb and gutter, add subdrain, and
revised grading. The trail on the north side was designed to accommodate an ultimate 3-lane section,
this trail will remain as-designed, grading between new back of curb and trail will be revised
accordingly.
B. Update estimated project quantities as required.
-2-
V:\Projects\2020\120.0783.01\Administration\Agmt_2021-08-13_SA02Scope.docx
C. Revise Ashworth Road plan and profile drawings.
D. Revise temporary easement areas and create new exhibit, if required.
E. Revise staging plans as appropriate.
F. Revise geometric, staking and jointing details.
G. Revise currently designed and design new storm sewer on Ashworth Road in the revised section.
Storm sewer will be designed to accommodate the ultimate 3-lane section with the trunk sewer placed
at the appropriate offset.
H. Create additional storm sewer design drawings and update tabulation to convey storm sewer design.
I. Revise water main profile design within the effected area to maintain 5.5-feet of cover.
J. Revise pollution prevention plan drawings as necessary.
K. Update the 3D design model and re-display cross sections in the affected area.
L. Provide updated CAD files to the Contractor, including 3D surfaces.
M. Issue a design revision PDF with changes noted. Individual sheets will be provided as well as a new
complete set of drawings.
III. CONSTRUCTION SERVICES
The Consultant will perform the following tasks related to construction administration.
A. Review shop drawings for added storm sewer structures. Eight (8) additional structures are
anticipated.
B. Attend bi-weekly, on-site construction meeting for the duration of the construction. Scope includes
attending 26 regular construction meetings between September 2021 and October 2022.
C. Attend a winter 2021 walk through with the Contractor and City staff. Prepare punch-list of items
needed to be complete prior to winter shut down.
D. Attend a final walk through at construction completion with the Contractor and City staff. Prepare a
punch-list of items needed to be complete prior to project acceptance.
IV. COMPENSATION
In consideration of the professional services provided herein, the City agrees to pay the Consultant the
following sum, NOT-TO-EXCEED, including any authorized reimbursable expenses, pursuant to the
Schedule of Fees set forth in Attachment 3 of the original agreement. The compensation schedule as set
forth in Article 3 of the original agreement is amended as follows:
-3-
V:\Projects\2020\120.0783.01\Administration\Agmt_2021-08-13_SA02Scope.docx
Basic Services of the Consultant
Approved
Agreements
Supplemental
Agreement
No. 02 Total
A.Project Management $31,000 $31,000
B.Topographic Survey $21,900 $21,900
C.Boundary Survey $6,500 $6,500
D.Wetland and Stream Delineation $6,000 $6,000
E.Threatened Endangered Species Habitat Survey $2,000 $2,000
F.Phase I Environmental Site Assessment $3,100 $3,100
G.Cultural Resources $18,000 $18,000
H.Intersection Alternatives Analysis $21,600 $21,600
I.Preliminary Roadway Design $61,900 $61,900
J.Right-of-Way Layout and Plot Plans $7,500 $7,500
K.Right-of-Way Plats $17,000 $17,000
L.Right-of-Way Acquisition $45,700 $45,700
M.Traffic Signal and Lighting Design $24,200 $24,200
N.Final Roadway Design $85,100 $12,000 $97,100
O.Geotechnical Investigation $20,000 $20,000
P.Gas Main Relocation Staking $4,100 $4,100
SUBTOTAL (Hourly Rate + Expenses)$375,600 $12,000 $387,600
Construction Phase Services of the Consultant
Base
Agreement
Supplemental
Agreement
No. 02 Total
A.Bidding $4,700 $4,700
B.Construction Administration $45,000 $14,100 $59,100
C.Traffic Signal Construction Phase Services $14,800 $14,800
D.Record Drawings $5,100 $5,100
SUBTOTAL (Hourly Rate + Expenses)$69,600 $14,100 $83,700
TOTAL (Hourly Rate + Expenses)$445,200 $26,100 $471,300