CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 15, 2021
AGENDA ITEM:Consideration of approval of Change Order No. 2 to Meade, Inc for the
Waukee 10-Inch Project Meredith/NW 10th Street Distribution Main
increasing the contract amount by $16,843.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 is to increase the depth of cover
to 8 foot minimum of an estimated 950 feet of the 10-inch HDPE gas main along Meredith St. &
Alice’s Rd. this change will prevent having to lower the pipeline at a later date for future road
widening projects.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $16,843.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 2
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Tim Royer TR
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1I4
Change Order 02
City of Waukee Department of Public Works
805 University Avenue Distribution __
Waukee, IA 50263 Owner-Finance __
515-978-7920 Fax 515-987-3979 Owner- Public Works __
Engineer __
Contractor __
Contractor Meade Inc.
625 Willowbrook Center Parkway
Waukee 10-Inch Project
Meredith/NW 10th St.
Willowbrook, IL 60527
708-588-2500 ph
$1,024,210.00
2
11/2/2021
THE CONTRACT IS CHANGED AS FOLLOWS
ITEM NO.ITEM CODE UNIT PRICE QUANTITY VALUE ADJUSTMENT
ADJUSTMENT
6 NEW ITEM $16,843.00 1 $16,843.00
$16,843.00
$1,024,210.00
$11,169.90
$1,035,379.90
$16,843.00
$1,052,222.90
7 Days
Prepared By Recommended By Checked By
USDI MEADE Inc.City of Waukee
Owner City of Waukee
Date
Date
Date
Date
The Original Contract Sum Was
Net Change by Previously Authorized Change Orders
The Contract Sum Prior to the Change Order was
The Contract Sum will be Increased by this Change Order in the Amount of
The new Contract Sum Including this Change Order will be
The Contract Time will be Changed by
__ >
$500.00 Department of Director
$501.00 to $2500.00 City Administrator
x__________________________________________
x__________________________________________
$2501 City Council Approved or Ratified at Meeting on
__ <
__
__
Title: Engineer Title: Title
Date: 11-02-2021 Date: Date
Signature Signature Signature
Name: Anthony Everette Name: Name
Project Title
Waukee Project File Number
Original Contract Amount
Change Order Number
Date
DESCRIPTION
8-foot minimum depth of cover for 950ft of 10-inch