HomeMy WebLinkAbout2021-11-15-I01I_13 2021 University Ave Pavement Patching_Pmt Est 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: November 15, 2021 AGENDA ITEM:Consideration of approval of Payment Estimate No. 1 (Final) to Q3 Contracting, Inc. for the 2021 University Avenue Pavement Patching project in the amount of $141,543.61. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Q3 Contracting, Inc. requested Payment Estimate No. 1 (Final) for the work completed on the 2021 University Avenue Pavement Patching project in the amount of $141,543.61. Veenstra & Kimm, Inc. has reviewed the payment estimate and recommends payment. The partial payment is for the pay period October 1, 2021 to October 31, 2021. Work completed for this pay estimate is pavement patching. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $141,543.61 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Payment Estimate No. 1 (Final) ATTACHMENTS: I. Payment Estimate No. 1 (Final) II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1I13 West Des Moines, IA • Coralville, IA • Dubuque, IA • Mason City, IA • Sioux City, IA Cedar Rapids, IA • Rock Island, Il • Springfield, IL • Liberty, MO • Rochester, MN VEENSTRA & KIMM, INC. 3000 Westown Parkway • West Des Moines, Iowa 50266-1320 515-225-8000 • 515-225-7848(FAX) • 800-241-8000 (WATS) November 8, 2021 Rudy Koester Public Works Director City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA 2021 UNIVERSITY AVENUE PAVEMENT PATCHING PROJECT CHANGE ORDER NO. 1 PAY ESTIMATE NO. 1 (FINAL) Enclosed are three signed copies of Change Order No. 1 and Pay Estimate No. 1 (Final) in accordance with the contract between the City of Waukee and Q3 Contracting, Inc. for the 2021 University Avenue Pavement Patching project. Change Order No. 1 is to adjust the plan quantities to the as-constructed quantities. Pay Estimate No. 1 (Final) is for pavement patching. We recommend payment by the City Council of the City of Waukee to Q3 Contracting, Inc. in the amount of $141,543.61. We also recommend the retainage in the amount of $7,449.66 be paid 31 days after acceptance of the work by the City of Waukee. Please execute all copies of Change Order No. 1 and Pay Estimate No. 1 (Final) in the spaces provided. Please return one copy of each to Veenstra & Kimm, Inc., forward one copy to Q3 Contracting, Inc. with payment, and retain one copy for your files. Rudy Koester November 8, 2021 Page 2 If you have any questions or comments, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Andy Willcuts ARW:paj 275345 Enclosures cc: Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Beth Richardson, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Tara Kammerer, City of Waukee – w/enclosure (email) Q3 Contracting, Inc. Date: PAY ESTIMATE NO. 1 (FINAL) Project Title Contractor Original Contract Amount & Date $110,576.57 June 21, 2021 Pay Period August 11, 2021 to November 2, 2021 BID ITEMS Estimated Extended Quantity Value Description Unit Quantity Unit Price Price Complete Completed 1.1 LS 1 5,759.96$ 5,759.96$ 100%5,759.96$ 1.2 EA 53 356.73$ 18,906.69$ 65 23,187.45$ 1.3 SY 504 164.38$ 82,847.52$ 684.77 112,562.49$ 1.4 TONS 80 38.28$ 3,062.40$ 85.25 3,263.37$ 144,773.27$ 2.1 LS 1 4,220.00$ 4,220.00$ 100%4,220.00$ 4,220.00$ Q3 Contracting, Inc. 3990 Delaware Avenue Des Moines, Iowa 50313 2021 UNIVERSITY AVENUE PAVEMENT PATCHING PROJECT WAUKEE, IOWA November 5, 2021 8" PCC Pavement Removal and Replacement 1" Granular Subbase Night Work Original Contract Value Completed Change Order No. 1 Value Completed Traffic Control 8" PCC Pavement Removal and Replacement VEENSTRA & KIMM, INC. 3000 Westown Parkway West Des Moines, Iowa 50266-1320 515-225-8000 515-225-7848(FAX) 800-241-8000 (WATS) V-K Job No. 275345 SUMMARY Contract Price Value Completed Original Contract Price $110,576.57 144,773.27$ Approved Change Orders (list each)1 38,416.70$ 4,220.00$ TOTAL ALL CHANGE ORDERS 38,416.70$ 4,220.00$ Revised Contract Price 148,993.27$ 148,993.27$ Materials Stored -$ Value of Completed Work and Materials Stored 148,993.27$ Less Retained Percentage (5%)7,449.66$ Net Amount Due This Estimate 141,543.61$ Less Estimate(s) Previously Approved No.1 No.2 No.3 No.4 No.5 No.6 No. 7 No. 8 No. 9 No. 10 No. 11 No. 12 Less Total Pay Estimates Previously Approved -$ Amount Due This Estimate 141,543.61$ The amount 141,543.61$ is recommended for approval for payment in accordance with the terms of the contract. The amount of $7,449.66 is payable 31 days after final acceptance of the project. Quantities Complete Submitted By:Recommended By:Approved By: Signature:Signature:Signature: Name:Name:Name: Title:Title:Engineer Title: Date:Date:Date: Q3 Contracting, Inc.Veenstra & Kimm, Inc. V-K Job No. 275345