HomeMy WebLinkAbout2021-11-15-I01I_16 LWC North Trunk Sewer Extension Phase 1 Completion_Pmt Est 3AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: November 15, 2021 AGENDA ITEM:Consideration of approval of Payment Estimate No. 3 (Final) to J&K Contracting, LLC for the Little Walnut Creek North Trunk Sewer Extension – Phase 1 Completion project in the amount of $55,101.43. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: J&K Contracting, LLC requested Payment Estimate No. 3 (Final) for the work completed on the Little Walnut Creek North Trunk Sewer Extension – Phase 1 Completion project in the amount of $55,101.43. Veenstra & Kimm, Inc. has reviewed the payment estimate and recommends payment. The partial payment is for the pay period October 1, 2021 to October 31, 2021. Work completed for this pay estimate includes manholes and seeding. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $55,101.43 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Payment Estimate No. 3 (Final) ATTACHMENTS: I. Payment Estimate No. 3 (Final) II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1I16 West Des Moines, IA • Coralville, IA • Dubuque, IA • Mason City, IA • Sioux City, IA Cedar Rapids, IA • Rock Island, Il • Springfield, IL • Liberty, MO • Rochester, MN VEENSTRA & KIMM, INC. 3000 Westown Parkway • West Des Moines, Iowa 50266-1320 515-225-8000 • 515-225-7848(FAX) • 800-241-8000 (WATS) November 9, 2021 Rudy Koester Director of Public Works City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA LITTLE WALNUT CREEK NORTH TRUNK SEWER EXTENSION - PHASE 1 COMPLETION PAY ESTIMATE NO. 3 (FINAL) CHANGE ORDER NO. 2 Enclosed are three copies of executed Pay Estimate No. 3 (Final) for work on the Little Walnut Creek North Trunk Sewer Extension – Phase 1 Completion project, under the contract between the City of Waukee and J&K Contracting, LLC. dated August 9, 2021. The partial payment estimate is for the period October 1, 2021 to October 31, 2021. We have checked the estimate and recommend payment to J&K Contracting, LLC in the amount of $55,101.43. Please sign all copies of Pay Estimate No. 3 (Final) in the space provided and return one signed copy of the partial payment estimate to our office. Please forward one signed copy of Pay Estimate No. 3 (Final) with payment to J&K Contracting, LLC. Pay Estimate No. 3 (Final) is for manholes and seeding. Also enclosed are three copies of Change Order No. 2 for additional manhole materials and to adjust plan quantities to the as-constructed quantities in the amount of $28,401.50. Change Order No. 2 has been incorporated into Pay Estimate No. 3 (Final). Please sign all copies of Change Order No. 2 in the space provided and return one signed copy of the change order to our office. Please forward one signed copy of Change Order No. 2 along with Pay Estimate No. 3 (Final) to J&K Contracting, LLC. Rudy Koester November 9, 2021 Page 2 If you have any questions, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Andy Willcuts ARW:paj 275331R Enclosures cc: J&K Contracting, LLC Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Beth Richardson, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Date: PAY ESTIMATE NO. 3 (FINAL) Project Title Contractor Original Contract Amount & Date $1,045,000.00 August 9, 2021 Pay Period October 1, 2021 to November 2, 2021 BID ITEMS Estimated Extended Quantity Value Description Unit Quantity Unit Price Price Complete Completed 1.1 LS 1 79,535.00$ 79,535.00$ 100%79,535.00$ 1.2 LS 1 22,500.00$ 22,500.00$ 100%22,500.00$ 1.3 TONS 25 75.00$ 1,875.00$ 25 1,875.00$ 1.4 LS 1 11,500.00$ 11,500.00$ 100%11,500.00$ 1.5 TONS 33 100.00$ 3,300.00$ 77 7,700.00$ 1.6 LF 100 50.00$ 5,000.00$ - -$ 1.7 SY 1,350 2.00$ 2,700.00$ 1,350 2,700.00$ 1.8 LS 1 3,400.00$ 3,400.00$ 100%3,400.00$ 1.9 LF 20 300.00$ 6,000.00$ 40 12,000.00$ 1.10 LF 90 1,800.00$ 162,000.00$ 90 162,000.00$ 1.11 LF 3,073 200.00$ 614,600.00$ 3,073 614,600.00$ 1.12 EA 7 4,700.00$ 32,900.00$ 7 32,900.00$ 1.13 EA 4 6,600.00$ 26,400.00$ 5 33,000.00$ 1.14 EA 2 7,000.00$ 14,000.00$ 3 21,000.00$ 1.15 VF 179 90.00$ 16,110.00$ 179 16,110.00$ 1.16 VF 137 140.00$ 19,180.00$ 168 23,520.00$ 1.17 EA 1 24,000.00$ 24,000.00$ 1 24,000.00$ 1,068,340.00$ 2.1 Water Main Adjustment LS 1 12,196.00$ 12,196.00$ 100%12,196.00$ 12,196.00$ 3.1 Additional Manhole Material LS 1 5,061.50$ 5,061.50$ 100%5,061.50$ 5,061.50$ Change Order No. 2 Value Completed Mobilization Install Furnished 60" SW-301 Standard Manholes Internal Drop Connection 48" Manhole Extra Depth 60" Manhole Extra Depth Install Furnished 48" SW-301 Standard Manholes Erosion Control Rip-Rap Connection to Existing Manhole Original Contract Value Completed November 5, 2021 Stabilizing Material Seeding Rolled Erosion Control Product, Type 2 Install Furnished 24" Sanitary Sewer in Place Field Drain Tiles Abandon Well 24" Sanitary Sewer Augered in Place in Steel Casing 8" Sanitary Sewer in Place Change Order No. 1 Value Completed J&K Contracting, LLC 10703 Justin Drive Urbandale, Iowa 50322 LITTLE WALNUT CREEK NORTH TRUNK SEWER EXTENSION - PHASE 1 COMPLETION WAUKEE, IOWA VEENSTRA & KIMM, INC. 3000 Westown Parkway West Des Moines, Iowa 50266-1320 515-225-8000 515-225-7848(FAX) 800-241-8000 (WATS) V-K Job No. 275332 SUMMARY Contract Price Value Completed Original Contract Price $1,045,000.00 1,068,340.00$ Approved Change Orders (list each)1 12,196.00$ 12,196.00$ 2 28,401.50$ 5,061.50$ TOTAL ALL CHANGE ORDERS 40,597.50$ 17,257.50$ Revised Contract Price 1,085,597.50$ 1,085,597.50$ Materials Stored -$ Value of Completed Work and Materials Stored 1,085,597.50$ Less Retained Percentage (5%)54,279.88$ Net Amount Due This Estimate 1,031,317.63$ Less Estimate(s) Previously Approved No.1 498,235.81$ No.2 477,980.39$ No.3 No.4 No.5 No.6 No. 7 No. 8 No. 9 No. 10 No. 11 No. 12 Less Total Pay Estimates Previously Approved 976,216.20$ Amount Due This Estimate 55,101.43$ The amount 55,101.43$ is recommended for approval for payment in accordance with the terms of the contract. The amount of $54,279.88 is payable 31 days after final acceptance of the project. Quantities Complete Submitted By:Recommended By:Approved By: Signature:Signature:Signature: Name:Name:Name: Title:Title:Engineer Title: Date:Date:Date: J&K Contracting, LLC Veenstra & Kimm, Inc. V-K Job No. 275332