HomeMy WebLinkAbout2021-01-18-Resolution 2021-009_Award Contract, Little Walnut Creek North Trunk Sewer Phase 1-Water Main ExtensionsRESOLUTION 2021-009
RESOLUTION MAKING AWARD OF CONSTRUCTION
CONTRACT FOR THE LITTLE WALNUT CREEK NORTH
TRUNK SEWER - PHASE 1 AND WATER MAIN EXTENSIONS
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WAUKEE, STATE
OF IOWA:
Section 1. That the following bid for the construction of certain public improvements
described in general as the Little Walnut Creek North Trunk Sewer - Phase 1 and Water Main
Extensions, described in the plans and specifications heretofore adopted by this Council on January
18, 2021, be and is hereby accepted, the same being the lowest responsive, responsible bid received
for such work, as follows:
Contractor: Priority Excavating, LLC, of Clive, IA
Amount of bid: $1,427,080.00
Portion of project: All construction work
Section 2. That the Mayor and Clerk are hereby directed to execute the contract with the
contractor for the construction of the public improvements, such contract not to be binding on the
City until approved by this Council.
PASSED AND APPROVED this 18th day of January, 2021.
ATTEST:
V'
City Clerk
RESULTS OF VOTE:
AYE
Anna Bergman
X
R. Charles Bottenberg
X
Chris Crone
X
Larry R. Lyon
X
Ben Sinclair
X
Mayor
NAY ABSENT ABSTAIN