HomeMy WebLinkAbout2022-03-21 Resolution 2022-119_Set Public Hearing Date, Little Walnut Creek Trunk Sewer Extension Phase 5RESOLUTION 2022-119
RESOLUTION ORDERING CONSTRUCTION OF THE LITTLE
WALNUT CREEK TRUNK SEWER EXTENSION - PHASE 5,
AND FIXING A DATE FOR HEARING THEREON AND
TAKING OF BIDS THEREFOR
WHEREAS, it is deemed advisable and necessary to construct certain public improvements
described in general as the Little Walnut Creek Trunk Sewer Extension - Phase 5; and
WHEREAS, the City has caused to be prepared plans, specifications and form of contract,
together with estimate of cost, which are now on file in the office of the City Clerk for public
inspection, for the construction of the public improvements; and
WHEREAS, the plans, specifications and form of contract are deemed suitable for the
making of the public improvements; and
WHEREAS, before the plans, specifications, form of contract and estimate of cost may be
adopted, and a contract for the construction of the public improvements is entered into, it is
necessary, pursuant to Chapter 26, Code of Iowa, to hold a public hearing and to advertise for bids:
NOW,THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
WAUKEE, STATE OF IOWA:
Section 1. That it is hereby determined that it is necessary and advisable to construct certain
public improvements described in ,general as the Little Walnut Creek Trunk Sewer Extension -
Phase 5, in the manner set forth in the plans and specifications and form of contract, above referred
to, the cost thereof to be paid in accordance with the provisions as set out in the posted Notice to
Bidders and published Notice of Public Hearing; the public improvements being more generally
described as follows:
Construct Little Walnut Creek Trunk Sewer Extension— Phase 5 including all labor,
materials and equipment necessary for approximately 3,000 linear feet of 8-inch
through 24-inch diameter sanitary sewer in open cut and augured in steel casing,
water main service pipe, manholes, excavation and backfill, surface restoration and
miscellaneous associated work, including cleanup.
The Little Walnut Creek Trunk Sewer Extension — Phase 5 project is located along
NW 1 Oth Street north of NVl' Douglas Parkway.
Section 2. That the amount ofthe bid security to accompany each bid shall be in an amount
which shall conform to the provisions of the notice to bidders approved as a part of the
specifications.
BE IT FURTHER RESOLVED, that the City Clerk be and is hereby directed to post a
notice to bidders once in a relevant contractor plan room service with statewide circulation and a
relevant construction lead generating service with statewide circulation and on an internet site
sponsored by either the City or a statewide association that represents the City. Posting shall be
not less than thirteen clear days nor more than forty-five days prior to April 12, 2022, which is
hereby fixed as the date for receiving bids. The bids are to be filed prior to 2:00 P.M., on such
date.
The City Council hereby delegates to the City Administrator or his designee the duty of
receiving, opening and tabulating bids for construction of the Project. Bids shall be received and
opened as provided in the public notice and the results of the bids shall be considered at the meeting
of this Council on April 18, 2022, at 5:30 P.M.
BE IT FURTHER RESOLVED, that the City Clerk be and is hereby directed to publish
notice of hearing once in a legal newspaper, printed wholly in the English language, published at
least once weekly and having general circulation in this City. Publication shall be not less than
four clear days nor more than twenty days prior to the date hereinafter fixed as the date for a public
hearing on the plans, specifications, form of contract and estimate of costs for the project, the
hearing to be at 5:30 P.M. on April 18, 2022.
PASSED AND APPROVED this 21 st day of March, 2022.
Mayor
ATTEST:
" (0, AJU4,t)+
City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
Anna Bergman Pierce X
R. Charles Bottenberg X
Chris Crone X
Larry R. Lyon X
Ben Sinclair X