RESOLUTION ACCEPTING THE LITTLE WALNUT CREEK
NORTH TRUNK SEWER EXTENSION - PHASE 1
COMPLETION
WHEREAS, on the 30'" day of August, 2021, the Mayor and Clerk of the City of Waukee,
Iowa, entered into a construction contract with J&K Contracting, LLC, of Urbandale, IA, for the
construction of certain public improvements generally described as the Little Walnut Creek North
Trunk Sewer Extension - Phase 1 Completion; and
WHEREAS, the contractor has fully completed the construction of the public
improvements in accordance with the terms and conditions of the contract and plans and
specifications, as shown by the certificate of the Engineer filed with the Clerk on September 26,
2022:
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
WAUKEE, STATE OF IOWA:
Section 1. That the report of the Engineer be and the same is hereby approved and adopted,
and the public improvements are hereby approved and accepted as having been fully completed in
accordance with the plans, specifications and form of contract and the total final construction cost
thereof is hereby determined to be $1,085,597.50, as shown in the report of the Engineer.
PASSED AND APPROVED this 3`d day of October, 2022.
Mayor
ATTEST:
City Clerk
RESULTS OF VOTE:
AYE NAY ABSENT ABSTAIN
Anna Bergman Pierce
X
R. Charles Bottenberg
X
Chris Crone
X
Larry R. Lyon
X
Ben Sinclair
X