HomeMy WebLinkAbout2009-06-15-Resolutions 09-130_R-22 Force Main Extension - Award ContractTHE CITY OF WAUKEE,IOWA
RESOLUTION 09-130
APPROVING CONTRACT FOR COUNTY ROAD R-22 FORCE MAIN
EXTENSION PROJECT TO THE UNDERGROUND COMPANY IN THE
AMOUNT OF $11,500.00
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE,IOWA
WHEREAS,the City of Waukee,Iowa is a duly organized municipality within Dallas
County;AND,
WHEREAS,on March 9,2009,the Waukee City Council approved plans and
specifications for the Northview Drive Extension and 6th Street Improvements Project
(Resolution #09-44);AND,
WHEREAS,utility work for the Northview Drive Extension and 6th Street
Improvements Project is being done by The Underground Company of Carlisle,Iowa;
AND,
WHEREAS,the project engineer has solicited a quotation from The Underground
Company in the amount of$11,500.00 to bore pipe across County Road R-22 (a project
to be known as County Road R-22 Force Main Extension);AND,
WHEREAS,as the proposed quotation is 23 %below the Engineers Estimate of Cost and
as The Underground Company is currently working in the same vicinity within the City
of Waukee,City staff recommends moving forward with the Project in advance of the
WRA Treatment Plant Upgrade Project projected to begin later this year.
NOW THEREFORE BE IT RESOLVED by the City of Waukee City Council in
session this is"day of June 2009 that it hereby approves awarding the contract for
County Road R-22 Force Main Extension Project to The Underground Company in the
amount of$11,500.00.